SpaceX’s Crew Dragon gets tentative NASA target for first astronaut launch
New information from both NASA and the US Government Accountability Office (GAO) confirm that SpaceX is currently targeting – at least very tentatively so – Crew Dragon’s first launch with astronauts aboard no earlier than November 15th, 2019.
SpaceX is currently in the midst of a complex, high-stakes anomaly investigation after its flight-proven DM-1 Crew Dragon capsule suffered a catastrophic failure on April 20th. That investigation is nowhere near full closure due to the fact that the interests of NASA and the Commercial Crew Program (CCP) are equally interwoven into the work involved. Given the potential consequences of a similar failure occurring with astronauts (public or private) aboard, NASA is unlikely to accept anything less than a no-stone-left-unturned analysis and failure resolution, including any necessary design changes to Crew Dragon, no matter how far-reaching.
As NASASpaceflight.com’s Chris Gerbhardt notes, the Crew Dragon-related dates included in the NASA Flight Planning Integration Panel (FPIP) document are extremely tentative. They’re really only there to serve as placeholders for longer-term International Space Station planning, already a necessarily uncertain endeavor. Nevertheless, NASA’s NET November 15th 2019 planning date for Crew Dragon DM-2 (the first crewed test flight) was likely okayed by SpaceX – if not provided outright by the company – before going into an official FPIP.
In other words, November 15th is probably a real target but should be treated as an absolutely-positively-no-earlier-than launch date for Crew Dragon’s first astronaut-laden mission to the ISS. Back in late March (after DM-1’s successfully completion but before the capsule’s ground failure), anonymous Russian space industry sources confirmed that NASA’s DM-2 planning date was July 25th, while also indicating that the space agency was already preparing for delays that could push DM-2 as late as November 2019.
Specifically, an anonymous Roscosmos source told Russian outlet TASS that “the [DM-2] launch of Crew Dragon is likely to be postponed to November”. Given that that delay was rumored – albeit quasi-officially – and reported on nearly a month before Crew Dragon capsule C201 catastrophically exploded during testing, it doesn’t exactly inspire confidence in a November 2019 DM-2 planning date officially released by NASA more three months later.
Crew Dragon stumbles, but optimism remains
As is often said, things were going perfectly up to the point that they weren’t. Despite 2-3 months of NASA paperwork and review-related delays, SpaceX’s first flightworthy Crew Dragon performed flawlessly during orbital rendezvous, docking, departure, and reentry to the extent that NASA and SpaceX officials were joking on-webcast about their partial disbelief. NASA’s lengthy post-mission review effectively concluded as much, although there is always room for improvement.
Due to those aforementioned DM-1 delays (roughly early January to early March), DM-2’s Crew Dragon assembly and integration was delayed in turn to preserve access in case DM-1 revealed flaws or necessary changes. Things didn’t quite go as planned, but the delayed integration has turned out to be beneficial, preserving access to most of Dragon 2’s critical subsystems without requiring major disassembly before any anomaly-related changes are implemented.

Per a late-May update from CCP manager Kathy Lueders, SpaceX has effectively shifted its Crew Dragon hardware assignments over one to account for the loss of the DM-1 capsule, C201. The vehicle previously assigned to DM-2 has been reassigned to a critical in-flight abort (IFA) test, previously meant to use flight-proven C201. Per charts provided during Lueders’ presentation, SpaceX’s replacement DM-2 capsule (likely the capsule previously assigned to the following mission, Crew-1) is in a sort of holding pattern to allow for modifications that may be required after the DM-1 failure investigation concludes.
Per a previous December 2018 update from Lueders, SpaceX’s original DM-2 spacecraft (now assigned to IFA) was expected to be fully assembled, shipped to Pad 39A, and ready for launch by June 2019. Accounting for DM-1’s delays, that spacecraft could likely be ready for the abort test as early as July or August, which meshes with post-anomaly indications that IFA is now scheduled no earlier than fall (September 2019)

All things considered, a pragmatic analysis suggests that Crew Dragon‘s DM-2 launch will most likely happen no earlier than Q1 2020, although miracles (and nightmares) are certainly possible. For the time being, all that really matters to SpaceX is wrapping up the C201 failure investigation as quickly and accurately as possible. Only after the company has publicly announced the results of that investigation should any IFA or DM-2 launch dates be taken with anything less than a full shaker of salt.
Check out Teslarati’s Marketplace! We offer Tesla accessories, including for the Tesla Cybertruck and Tesla Model 3.
News
Tesla Full Self-Driving is taking over Europe: fourth country gets FSD approval
Tesla has secured regulatory approval for its Full Self-Driving (Supervised) system in Denmark, marking a significant step in the technology’s expansion across Europe.
Announced on June 9, the approval positions Denmark as the fourth European country to greenlight FSD Supervised, following the Netherlands, Lithuania, and Estonia.
Rollout to Danish vehicle owners is expected to begin soon, the company said.
The Danish Road Traffic Authority granted provisional approval after reviewing the original type approval issued by the Dutch vehicle authority (RDW) on April 10, 2026.
FSD Supervised now approved in Denmark 🇩🇰
Rollout will begin soon pic.twitter.com/Xpxwcme10k
— Tesla Europe, Middle East & Africa (@teslaeurope) June 9, 2026
This national recognition approach allows individual countries to bypass slower EU-wide harmonization processes, accelerating deployment. Lithuania activated the system on May 20, with Estonia following on May 29, demonstrating a rapid domino effect across the region.
FSD Supervised enables advanced driver assistance capabilities, including automatic steering, acceleration, braking, lane changes, and navigation through complex urban and rural environments. The system is designed for supervised use, as its name states, meaning drivers must remain attentive and ready to intervene at all times.
It adapts to diverse conditions, such as rain, night driving, and varied road types common in Denmark, but it is important to note that the tech is not fully autonomous.
Following a launch in Europe just a few months ago, with its first approval coming in the Netherlands, Tesla is just now highlighting the successful start.
Early data from the Netherlands highlights strong safety performance. Between April 10 and June 5, vehicles using FSD Supervised recorded 3.5 times fewer collisions than manual driving overall, with zero crashes reported on highways across more than 16.6 million kilometers driven.
These results underscore the potential of the technology to enhance road safety when properly supervised.
Tesla’s European push builds on its global footprint, now reaching 12 countries with FSD Supervised availability. The software receives continuous over-the-air updates, improving performance based on real-world data from millions of miles.
In Denmark, owners with compatible hardware—particularly newer vehicles equipped with Hardware 4 (HW4)—are anticipated to gain access first, though exact timelines and eligibility details will be confirmed during rollout.
This approval reflects growing regulatory confidence in supervised autonomy across Europe. As more nations recognize the Dutch certification, Tesla continues to demonstrate how its AI-driven approach can navigate real-world driving scenarios effectively. Denmark’s addition strengthens Tesla’s position in the region, paving the way for broader adoption on a continent that his been surprisingly slow to adopt the technology.
With FSD Supervised now approved in four European markets in just two months, the technology is steadily advancing toward wider availability. Tesla aims to refine the system further through ongoing data collection and software iterations, supporting its vision for safer and more efficient transportation.
News
Tesla revises FSD transfer policy on new Cybertruck trim, causing cancellations
Tesla has apparently revised the policy it previously had listed for Full Self-Driving transfers on the newest All-Wheel-Drive Cybertruck that the company had sold for a steal price of just $59,000 earlier this year.
After initially stating that customers who bought the pickup would be able to transfer FSD purchases, Tesla recently changed the language in those terms and conditions to reflect that this would no longer be the case.
Tesla launches new Cybertruck trim with more features than ever for a low price
The adjustment in terminology has caused a handful of orderers to cancel their reservations due to the loss of FSD transfer:
Just cancelled my 59k CT order today. My screenshot from that day of order (feb 20th) clearly shows that it would be eligible.
Terms were retroactively modified. Our 2020 Y and 2023 S are just fine for now. pic.twitter.com/D9PFnId1B4
— Ryan Scanlan 👥 (@Xenius) June 8, 2026
Tesla said orders for the new Cybertruck AWD must be placed by March 31, 2026, to qualify for the FSD transfer. The language in the document from earlier this year explicitly states that they “may qualify” for the transfer program, but the date of March 31 is explicitly mentioned.
Additionally, Tesla Delivery Advisors reached out to some orderers of the AWD Cybertruck, who were told there was “an update to the eligibility of the Full Self-Driving (Supervised) transfer.” Tesla stated they could:
- proceed without the transfer,
- upgrade to a Premium or Cyberbeast trim and request an FSD Transfer
- cancel the order and be refunded the $250 order fee.
Tesla turning around and changing these terms will undoubtedly result in a handful of cancellations on the part of those who have placed an order for this truck. They could pay $99 per month for an FSD subscription, which is now the only option available, but having purchased the suite outright on another vehicle and being told the transfer policy would be upheld, only to have it cancelled, is a tough pill to swallow.
These moves were also made by Tesla just before deliveries were set to begin on the Cybertruck AWD configuration. Reservation holders have started receiving VINs for their trucks, and Tesla is preparing to hand over the first units.
It’s a disappointing move from Tesla that will undoubtedly make some of its fans who have bought the truck frustrated.
Elon Musk
Tesla tipped its hand at where Robotaxi is heading next
In the world of autonomous ride-hailing, there are only a handful of names. Among those few companies lies a strategy play by each to keep the opposition on their toes. Tesla, on the other hand, already tipped its hand at where it is headed next.
Tesla has signaled its next major push in the autonomous ride-hailing market by filing for an Autonomous Vehicle Network Company permit in Nevada (Docket 26-05015). Through Tesla Robotaxi, LLC, the company seeks approval to operate up to 5,000 robotaxis in Clark County, including high-traffic areas like Las Vegas and Henderson airports, within the first 12 months of launch.
This filing builds on Tesla’s earlier testing approvals from the Nevada DMV in September 2025 and preparations such as maintenance hubs in the Las Vegas area. Nevada represents a strategic expansion into a major tourist destination, where high visitor volumes could drive strong utilization and showcase the reliability of unsupervised autonomy to a broad audience.
We’d have to assume this means Tesla is targeting Las Vegas, and it’s a great move from a business perspective.
Vegas is such a melting pot of people from all around the country and the world. It will expose people from all corners of the globe to Tesla’s autonomy capabilities https://t.co/Qz3fQmhULF pic.twitter.com/Du5pj2RyWC
— TESLARATI (@Teslarati) June 6, 2026
Approval would mark a significant step toward commercial operations in a new state, following progress in Texas.
Tesla’s shareholder decks and earnings calls have clearly outlined these ambitions. In the Q4 2025 shareholder deck, the company listed planned Robotaxi coverage for the first half of 2026, explicitly naming Las Vegas alongside Phoenix, Miami, Orlando, and Tampa, with Dallas and Houston already advancing. Austin was noted as “ramping unsupervised,” while the Bay Area remained in safety-driver mode.
By Q1 2026, the deck updated statuses to reflect launches in Dallas and Houston, with “preparations underway” for the remaining cities, including Las Vegas. Paid Robotaxi miles nearly doubled sequentially in Q1, underscoring momentum even as broader timelines adjusted slightly for regulatory and operational readiness.
On earnings calls, CEO Elon Musk and executives have emphasized a phased rollout prioritizing safety. Unsupervised operations in Texas have shown strong results with no reported accidents or injuries in the program. Tesla continues groundwork in additional major U.S. metros through testing and permitting, positioning it to scale quickly once approvals clear.
This Nevada move aligns with Tesla’s vision of transforming from an EV maker into an AI and robotics leader. The forthcoming Cybercab, which started production at Giga Texas in April, is expected to eventually dominate the fleet, replacing many Model Y vehicles and driving down costs to enable affordable rides.
For investors and the industry, this signals Tesla’s intent to dominate key Sun Belt and tourist markets where weather, regulations, and demand favor rapid scaling. Success in Las Vegas could validate the model for denser urban and high-tourism environments, accelerating the shift toward a future where robotaxis generate meaningful revenue.
Las Vegas will also expand knowledge among the general public at Tesla’s capabilities, helping people experience driverless ride-hailing from several companies during their time on The Strip.