News
SpaceX preparing giant crane to assemble Starship’s first Florida launch tower
SpaceX has begun staging and assembling parts of a giant crane it will soon need to stack Starship’s first East Coast launch tower and install other major launch pad components.
The presence of the base of that crane at SpaceX’s NASA Kennedy Space Center (KSC) Launch Complex 39A was visually confirmed by NASASpaceflight.com photographers during a weekly aerial tour of the area on June 3rd. Four days later, Teslarati photographer Richard Angle observed more major crane components on their way to Pad 39A, including the crane’s cabin.
More likely than not, the crane SpaceX or its contractor has begun assembling at 39A is a Liebherr LR 11350, the same kind of crane the company used to assemble Starship’s first orbital launch site and tower in South Texas. In fact, given how few LR 11350s there are in existence, it’s entirely possible that it’s the exact same crane. Assembly of that crane began around April 2021 and took a month and a half, at which point it was finally ready to lift an extended boom long enough to assemble a tower almost 500 feet (~150 meters) tall.

Pad 39A’s Starship launch tower is expected to be very similar to Starbase’s, although it will undoubtedly carry over numerous design changes thanks to lessons learned while building and outfitting the first tower. In fact, SpaceX has already assembled five of the nine individual sections that will eventually be stacked to form that tower, and one such change is already obvious. Instead of stacking each tower section as soon as its barebones framework is complete, SpaceX is taking a more methodical approach to its second launch tower. In an apparent attempt to limit the amount of work that needs to be done at Pad 39A itself, each of those segments is being thoroughly outfitted with secondary structures (ladders, doors, walkways, frames, raceways, etc.) before stacking.
SpaceX may even pre-install most of the thousands of feet of plumbing needed to connect a Starship to ground systems located around 90 meters (~300 ft) below it. Once stacked, each section – including all those partial propellant and gas lines – will still need to be joined together, but that process should be far easier than fully installing all the systems the tower needs to do its job. Outfitting Starbase’s launch tower, for example, took SpaceX around half a year and, to some extent, is still ongoing 11 months after the final stack. That likely explains why Starship’s 39A tower section assembly appears to be taking more time. With any luck, partially combining the outfitting and section assembly stages will significantly expedite final assembly, as far less work will need to be done at extreme heights or require a skyscraper-sized crane.

Through Starbase, SpaceX has already demonstrated the ability to stack a Starship launch tower from its unoccupied concrete base to its final height of ~145 meters (~475 ft) in about two months flat. While SpaceX will have to slalom its way around Pad 39A’s busy launch manifest, there’s no reason to believe that Starship’s first Florida launch tower won’t be stacked at least as quickly.
Aside from the arrival of crane parts, SpaceX has also made great progress on the Starship launch site itself. In the last few weeks, the company appears to have completed several significant concrete pours on the tower base. SpaceX has also installed all six of the pedestal-like orbital launch mount’s legs after months of foundation work. Elsewhere at Cape Canaveral, a different team has made excellent progress assembling the massive donut-like platform that will sit on top of those legs. Due to its extreme weight (possibly around 300 metric tons, per Elon Musk’s comments on the Starbase mount), the same LR 11350 crane will also be needed for that major installation milestone.

Plenty of parts are still missing, of course. Four tower sections still need to be assembled. Starship’s first Florida launch tower will need its own set of two ‘chopstick’ arms for lifting and (maybe) catching Starship and Super Heavy, as well as a third swinging quick-disconnect arm to connect Starship to ground systems. Aside from delivering several new tanks, SpaceX has also made no apparent progress on adding a massive methane propellant farm to Pad 39A, and it’s possible that the pad’s oxygen farm will also need to be expanded. Propellant storage has proven to be a major headache for SpaceX at Starbase.
Nonetheless, SpaceX is making great progress on most of the most difficult parts of Starship’s first Florida launch site, and there’s a good chance that just like its launch mount, work on the pad’s tower arms is already underway somewhere offsite. A great deal of work remains to be done but SpaceX is still well on its way to launching Starships out of Kennedy Space Center in the not-too-distant future.
News
Tesla Robotaxi appears to be heading to a new U.S. city
Things are expanding for Robotaxi, but the big sign that it is really moving along greatly will be with the expansion to a new city. Tesla has not gone outside of Austin or the Bay Area as of yet, and launching in a new city will be a great indicator of progress.
Tesla Robotaxi appears to be heading to a new U.S. city, and although the company has revealed plans to launch in six new metros this year, it has yet to establish a new location outside of Austin and the Bay Area of California, where it has operated since last Summer.
A lot full of Model Y vehicles was spotted in Henderson, a town just north of Las Vegas, but there seems to be more than just this hint indicating that the Sin City will be the next location to offer potentially driverless rides in a Tesla using its Full Self-Driving suite.
These Model Ys are not your typical vehicles, as they are fitted with hardware that is only on Robotaxis: a rear camera washer is the dead giveaway:
🚨 These rear camera washers are only present on Robotaxi vehicles
Maybe Las Vegas is the next city to get the Robotaxi suite 😀 https://t.co/my3da5L4zc pic.twitter.com/jYFQuX1j2E
— TESLARATI (@Teslarati) March 17, 2026
The photos and video of the lot were taken by TheZacher on X, who spotted the Model Y fleet in the Henderson parking lot.
The rear camera washer is the main piece of evidence here that indicates Tesla could be looking to expand Robotaxi to Las Vegas, a major ride-hailing hot spot, as it is one of the biggest tourist attractions in the United States. Ride-sharing is a major industry in Vegas, especially for those who are staying off the Strip.
Tesla has also been extremely transparent that Vegas is on its radar for the Robotaxi fleet, as it revealed last year that it was one of five new U.S. cities that it planned to launch the ride-hailing service in this year.
Tesla confirms Robotaxi is heading to five new cities in the U.S.
The others were Phoenix, Dallas, Houston, and Miami.
Things are expanding for Robotaxi, but the big sign that it is really moving along greatly will be with the expansion to a new city. Tesla has not gone outside of Austin or the Bay Area as of yet, and launching in a new city will be a great indicator of progress.
It will also give Tesla a new benchmark against rival company Waymo, which has operated in Las Vegas for some time.
News
Tesla Roadster gets new unveiling date once again
Musk announced last year that the unveiling, which initially happened back in 2018, would take place on April Fool’s Day. Initial deliveries at the 2018 event were slotted for 2020, but delays in the project, as well as prioritization of other things, continued to push the Roadster back.
The Tesla Roadster is perhaps the most anticipated vehicle in the company’s history, but those who have been waiting anxiously for it will have to push their timelines back once again.
Tesla CEO Elon Musk has revealed that the company is once again pushing back the unveiling event that was originally planned for April 1. It will now take place “probably in late April.”
True.
New Roadster unveil probably in late April. https://t.co/NShZxpK5cI
— Elon Musk (@elonmusk) March 17, 2026
Musk announced last year that the unveiling, which initially happened back in 2018, would take place on April Fool’s Day. Initial deliveries at the 2018 event were slotted for 2020, but delays in the project, as well as prioritization of other things, continued to push the Roadster back.
There has been so much hype about the Roadster that people are right to be excited about the prospect of its existence.
Musk’s most recent rumblings about the vehicle came last Fall, when he appeared on the Joe Rogan Experience podcast, where he once again hinted the car would be able to hover for a short period.
He said:
“Whether it’s good or bad, it will be unforgettable. My friend Peter Thiel once reflected that the future was supposed to have flying cars, but we don’t have flying cars. I think if Peter wants a flying car, he should be able to buy one…I think it has a shot at being the most memorable product unveiling ever. [It will be unveiled] hopefully before the end of the year. You know, we need to make sure that it works. This is some crazy technology in this car. Let’s just put it this way: if you took all the James Bond cars and combined them, it’s crazier than that.”
Additionally, he said the vehicle would not be something that would prioritize safety. Musk said that “If safety is your number one goal, do not buy the Roadster.” It’s made for speed and excitement, not for grocery-getting.
Elon Musk just said some crazy stuff about the Tesla Roadster
As the April 1 unveiling event that was originally planned was nearing without any communication to fans, media, or anyone who would potentially be in attendance, it seemed to be pretty obvious that Tesla was not ready to pull the trigger on the event quite yet.
There could be some last-minute things to finalize, or it could be something else. One thing is for certain, though: we are not super surprised that things were moved back.
Tesla has definitely been putting some things in motion for the Roadster. A few months back, Tesla started to ramp up hiring for the Roadster, and earlier in March, it submitted a patent application for a new seat design.
Elon Musk
Tesla named by U.S. Gov. in $4.3B battery deal for American-made cells
What began as an open secret in the energy industry was confirmed by the U.S. Department of the Interior on Monday: Tesla is the buyer behind LG Energy Solution’s blockbuster $4.3 billion battery supply agreement.
What began as an open secret in the energy industry is becoming more real after the U.S. Department of the Interior named Tesla as the stakeholder in the LG Energy Solution’s blockbuster $4.3 billion battery supply agreement.
Tesla and LG Energy Solution are expanding their partnership to build a LFP prismatic battery cell manufacturing facility in Lansing, Michigan, launching production in 2027. The announcement, made as part of the Indo-Pacific Energy Security Summit results, ends months of speculation.
“American-made cells will power Tesla’s Megapack 3 energy storage systems produced in Houston, creating a robust domestic battery supply chain.”, notes a press release on the U.S. Department of the Interior website.
Tesla has long utilized China’s Contemporary Amperex Technology Co. (CATL), the world’s largest LFP battery maker, as one of its primary suppliers. That relationship made financial sense for years, considering that Chinese LFP cells were cheap, abundant, and reliable. But with escalated tariffs on Chinese imports and an increasingly growing Tesla Energy business that’s particularly reliant on LFP cells for products including its Megapack battery storage units designed for utilities and large-scale commercial projects.
The announcement of a deepened partnership between LG Energy Solution and Tesla has strategic logic for both parties. For Tesla, it secures a tariff-compliant, domestically produced battery supply for its fast-growing energy division. LGES, now producing LFP batteries in Michigan, becomes the only major supplier currently scaling U.S. production, outpacing rivals like Samsung SDI and SK On. LG Energy Solution’s Lansing plant, formerly known as Ultium Cells 3, was previously operated as a joint venture with General Motors. LGES acquired GM’s stake in May 2025 and now fully owns the site, with a production capacity of 50 GWh per year. LG Energy said the contract includes options to extend the supply period by up to seven years and boost volumes based on further consultations.
For the broader industry, the ripple effects are significant. This deal signals that domestic battery manufacturing can be financially viable and not just aspirational. Utilities, energy developers, and rival automakers will take note as American-made LFP supply becomes a competitive reality rather than a distant promise.
For consumers, the benefits will take time but are real. A more resilient, U.S.-based supply chain means fewer price shocks from trade disputes, more stable Megapack availability for the grid storage projects that reduce electricity costs, and long-term downward pressure on energy storage prices as domestic production scales.
Deliveries are set to begin in 2027 and run through mid-2030, and as grid storage demand accelerates, reliable, US-made battery supply is no longer a future ambition. It is becoming a core requirement of the country’s energy strategy.