News
SpaceX preparing giant crane to assemble Starship’s first Florida launch tower
SpaceX has begun staging and assembling parts of a giant crane it will soon need to stack Starship’s first East Coast launch tower and install other major launch pad components.
The presence of the base of that crane at SpaceX’s NASA Kennedy Space Center (KSC) Launch Complex 39A was visually confirmed by NASASpaceflight.com photographers during a weekly aerial tour of the area on June 3rd. Four days later, Teslarati photographer Richard Angle observed more major crane components on their way to Pad 39A, including the crane’s cabin.
More likely than not, the crane SpaceX or its contractor has begun assembling at 39A is a Liebherr LR 11350, the same kind of crane the company used to assemble Starship’s first orbital launch site and tower in South Texas. In fact, given how few LR 11350s there are in existence, it’s entirely possible that it’s the exact same crane. Assembly of that crane began around April 2021 and took a month and a half, at which point it was finally ready to lift an extended boom long enough to assemble a tower almost 500 feet (~150 meters) tall.

Pad 39A’s Starship launch tower is expected to be very similar to Starbase’s, although it will undoubtedly carry over numerous design changes thanks to lessons learned while building and outfitting the first tower. In fact, SpaceX has already assembled five of the nine individual sections that will eventually be stacked to form that tower, and one such change is already obvious. Instead of stacking each tower section as soon as its barebones framework is complete, SpaceX is taking a more methodical approach to its second launch tower. In an apparent attempt to limit the amount of work that needs to be done at Pad 39A itself, each of those segments is being thoroughly outfitted with secondary structures (ladders, doors, walkways, frames, raceways, etc.) before stacking.
SpaceX may even pre-install most of the thousands of feet of plumbing needed to connect a Starship to ground systems located around 90 meters (~300 ft) below it. Once stacked, each section – including all those partial propellant and gas lines – will still need to be joined together, but that process should be far easier than fully installing all the systems the tower needs to do its job. Outfitting Starbase’s launch tower, for example, took SpaceX around half a year and, to some extent, is still ongoing 11 months after the final stack. That likely explains why Starship’s 39A tower section assembly appears to be taking more time. With any luck, partially combining the outfitting and section assembly stages will significantly expedite final assembly, as far less work will need to be done at extreme heights or require a skyscraper-sized crane.

Through Starbase, SpaceX has already demonstrated the ability to stack a Starship launch tower from its unoccupied concrete base to its final height of ~145 meters (~475 ft) in about two months flat. While SpaceX will have to slalom its way around Pad 39A’s busy launch manifest, there’s no reason to believe that Starship’s first Florida launch tower won’t be stacked at least as quickly.
Aside from the arrival of crane parts, SpaceX has also made great progress on the Starship launch site itself. In the last few weeks, the company appears to have completed several significant concrete pours on the tower base. SpaceX has also installed all six of the pedestal-like orbital launch mount’s legs after months of foundation work. Elsewhere at Cape Canaveral, a different team has made excellent progress assembling the massive donut-like platform that will sit on top of those legs. Due to its extreme weight (possibly around 300 metric tons, per Elon Musk’s comments on the Starbase mount), the same LR 11350 crane will also be needed for that major installation milestone.

Plenty of parts are still missing, of course. Four tower sections still need to be assembled. Starship’s first Florida launch tower will need its own set of two ‘chopstick’ arms for lifting and (maybe) catching Starship and Super Heavy, as well as a third swinging quick-disconnect arm to connect Starship to ground systems. Aside from delivering several new tanks, SpaceX has also made no apparent progress on adding a massive methane propellant farm to Pad 39A, and it’s possible that the pad’s oxygen farm will also need to be expanded. Propellant storage has proven to be a major headache for SpaceX at Starbase.
Nonetheless, SpaceX is making great progress on most of the most difficult parts of Starship’s first Florida launch site, and there’s a good chance that just like its launch mount, work on the pad’s tower arms is already underway somewhere offsite. A great deal of work remains to be done but SpaceX is still well on its way to launching Starships out of Kennedy Space Center in the not-too-distant future.
DIY
Tesla owner fixes common feature complaint with crafty DIY retrofit
Tesla owners have long griped about the wireless phone charger in the Model Y and other vehicles. It often turns smartphones into miniature ovens rather than reliably topping them up.
Software engineer and Model Y owner Michał Gapiński tackled this issue head-on with a clever DIY upgrade, swapping the cooled wireless charger pad from the China-made Model YL in for the one that came standard in his vehicle.
There are several key differences between the U.S.-built Model Y’s wireless charging pad and the one that Tesla has been installing in the Model YL. The one installed in U.S.-built vehicles lacks active cooling and relies on basic heat dissipation, leading to rapid temperature buildup during charging. In contrast, the Model YL integrates a small fan for active cooling.
Will it fit? Fingers crossed, I want a first YL charger deployed in the regular juniper pic.twitter.com/wWDqSNFVkW
— Michał Gapiński (@mikegapinski) June 2, 2026
This design maintains lower temperatures even in warm ambient conditions, though it does not support faster Qi2 charging on iPhones. The connector matches exactly, making physical swaps feasible on compatible consoles, but coding is required to enable full functionality.
Owners in the U.S. have complained about the wireless charging pad, with many reporting that overheating is fairly common. Within 20 or 30 minutes of placing a phone on the wireless charging pad, many have reported overheating messages on their phones, which halt charging and essentially turn the pad into a fancy place to rest your phone.
Many owners have opted to simply plug their phones into a charging cord. Tesla has acknowledged the problem by releasing several solutions for owners, including a relatively new feature that allows you to simply turn off the charging and simply act as a holder for your phone while driving.
Gapiński said that he sourced the cooled pad affordably from China, and it cost under $200 for the part.
He removed the existing console charger, swapped in the new unit, confirming a perfect connector fit, and handled the trim differences. Since the parameter isn’t fully secured, he enabled it through custom coding outside official Toolbox.
Connector is identical, she fits, now time to code it. https://t.co/Y9idgDrpCq pic.twitter.com/uwwgq6blg7
— Michał Gapiński (@mikegapinski) June 2, 2026
The fan activates quietly, blending with AC and seat cooling. He reported the installation was effective and the wireless charging pad worked perfectly; it even kept the phone cool as it stayed at just 86 degrees Fahrenheit. Many times, the wireless charging pad will bring the phone’s temperature well above 100 degrees, sometimes even being relatively hot to the touch.
The retrofit worked, no issues. First Model Y with a cooled wireless charger! No QI2/faster charging on the iPhone but it does not boil the phone even when it is 30 degrees outside.
The fan kicks in, it is not audible especially with the air conditioning and seat cooling. The… https://t.co/JOyR8Tb1Yo pic.twitter.com/kJcYhQIlYq
— Michał Gapiński (@mikegapinski) June 2, 2026
This retrofit highlighted an elegant, owner-driven solution to a factory shortcoming. It is expected that Tesla will begin installing the cooled charging pads into new cars in the U.S. soon, and hopefully, it will offer some sort of retrofit service or kit to owners here who want to use the charging pad effectively.
For those who love to tinker, it’s an accessible upgrade, proving that innovation thrives beyond the production line.
News
Tesla exec says Roadster unveil is soon — for real this time
The Tesla Roadster unveiling could be coming “in a few weeks,” according to the company’s Chief Designer Franz von Holzhausen, who said at the Tesla Takeover Europe Event in Austria that the all-electric hypercar could finally make its way to the production line after years of anticipation.
Von Holzhausen delivered the news just days after The Information reported that Tesla planned to push the Roadster unveiling to August. It was slated for both April and May of this year, but now it seems the company is leaning toward a late Summer event to cap off the heat with perhaps its most anticipated vehicle of all-time.
🚨 Tesla Chief Designer Franz Von Holzhausen, speaking to the crowd at Tesla Takeover Europe, said at the event that the Roadster is coming “in a few weeks,”
Multiple attendees have confirmed this pic.twitter.com/B1v6yb2Geq
— TESLARATI (@Teslarati) June 6, 2026
Franz has been with Tesla since 2008, and has played a pivotal role in the iconic design language the company has utilized with its vehicles. Speaking to the crowd in Austria virtually, von Holzhausen’s comments injected fresh excitement into a project that has been plagued by delays for nine years.
The second-generation Roadster promises to redefine supercar standards. Tesla’s website still highlights ambitious targets: 0-60 mph in under 1.9 seconds (with optional SpaceX thruster pack potentially achieving 1.1 seconds or less), a top speed exceeding 250 mph, and a range of about 620 miles.
Equipped with a tri-motor all-wheel-drive setup delivering over 1,000 horsepower, the four-seater aims to blend blistering acceleration, everyday usability, and innovative features like cold gas thrusters for short-hop capabilities, technology that will combine the project with SpaceX.
But years after the company promised to start production, which was slated for 2020, the timeline for the Roadster has continued to shift.
Tesla has strung along those who have put $50,000 deposits down, as well as fans and enthusiasts of the company who have been long awaiting the company to bring forth a car truly designed for the human driver, and not autonomy. The Roadster is more than just a halo vehicle for Tesla; it showcases the company’s ability to push the boundaries while incorporating synergies from other Musk companies.
However, it has to make it to production, which is something Musk and Co. have pushed back repeatedly.
As Tesla navigates Robotaxi development and broader autonomy goals, the Roadster serves as a reminder of its performance roots. If von Holzhausen’s timeline holds, fans could witness this engineering marvel by late June or early July 2026. Whether a full unveiling, demo, or initial deliveries, it marks a milestone for electric supercars.
News
Tesla Roadster unveiling gets pushed again, but new event details emerge
Tesla has reportedly pushed the unveiling of the Roadster once again, but there are also evidently new details about the event that the company plans to show off.
The Information reported this morning that Tesla will now unveil, for the second time, the next-generation Roadster in August, a further delay from the multiple timeline that the company had previously stated.
The report has not been confirmed or denied by Tesla at any capacity.
It also states the unveiling event will take place in Texas, the same place that Tesla executives revealed in May would be the place of manufacture for the company’s highly-anticipated supercar, which boasts a top speed of over 250 MPH and 650 miles of range, according to its website.
Tesla is also expected to showcase the SpaceX package, which will be used for faster acceleration and potentially hovering capabilities, at the unveiling event, the report states. Musk has always planned for this to happen, but now it seems it is more realistic than ever
The report also states the Roadster unveiling is planned for August pic.twitter.com/By26XZIJzU
— TESLARATI (@Teslarati) June 5, 2026
The Roadster has had its unveiling date and manufacturing date pushed back on many occasions. It was set to start production in 2020, but the COVID-19 pandemic crippled supply chain operations, forcing Tesla to push its timeline back considerably.
However, COVID has been over for some time, and Tesla has still not managed to successfully schedule and execute an unveiling event, which is something fans and enthusiasts, as well as those who have put down a $50,000 deposit, have been waiting for.
The vehicle was close to completion last year, but Musk truly wanted Lars Moravy and Franz von Holzhausen to push the limits of the Roadster. In July of last year, Moravy said:
“Roadster is definitely in development. We did talk about it last Sunday night. We are gearing up for a super cool demo. It’s going to be mind-blowing; We showed Elon some cool demos last week of the tech we’ve been working on, and he got a little excited.”
It is important to note two things: Tesla has not confirmed these details, and the company has regularly pushed these dates back. Until Tesla sends out formal invitations with a concrete date, taking any unveiling event reports with a grain of salt is a good idea.