News
SpaceX preparing giant crane to assemble Starship’s first Florida launch tower
SpaceX has begun staging and assembling parts of a giant crane it will soon need to stack Starship’s first East Coast launch tower and install other major launch pad components.
The presence of the base of that crane at SpaceX’s NASA Kennedy Space Center (KSC) Launch Complex 39A was visually confirmed by NASASpaceflight.com photographers during a weekly aerial tour of the area on June 3rd. Four days later, Teslarati photographer Richard Angle observed more major crane components on their way to Pad 39A, including the crane’s cabin.
More likely than not, the crane SpaceX or its contractor has begun assembling at 39A is a Liebherr LR 11350, the same kind of crane the company used to assemble Starship’s first orbital launch site and tower in South Texas. In fact, given how few LR 11350s there are in existence, it’s entirely possible that it’s the exact same crane. Assembly of that crane began around April 2021 and took a month and a half, at which point it was finally ready to lift an extended boom long enough to assemble a tower almost 500 feet (~150 meters) tall.

Pad 39A’s Starship launch tower is expected to be very similar to Starbase’s, although it will undoubtedly carry over numerous design changes thanks to lessons learned while building and outfitting the first tower. In fact, SpaceX has already assembled five of the nine individual sections that will eventually be stacked to form that tower, and one such change is already obvious. Instead of stacking each tower section as soon as its barebones framework is complete, SpaceX is taking a more methodical approach to its second launch tower. In an apparent attempt to limit the amount of work that needs to be done at Pad 39A itself, each of those segments is being thoroughly outfitted with secondary structures (ladders, doors, walkways, frames, raceways, etc.) before stacking.
SpaceX may even pre-install most of the thousands of feet of plumbing needed to connect a Starship to ground systems located around 90 meters (~300 ft) below it. Once stacked, each section – including all those partial propellant and gas lines – will still need to be joined together, but that process should be far easier than fully installing all the systems the tower needs to do its job. Outfitting Starbase’s launch tower, for example, took SpaceX around half a year and, to some extent, is still ongoing 11 months after the final stack. That likely explains why Starship’s 39A tower section assembly appears to be taking more time. With any luck, partially combining the outfitting and section assembly stages will significantly expedite final assembly, as far less work will need to be done at extreme heights or require a skyscraper-sized crane.

Through Starbase, SpaceX has already demonstrated the ability to stack a Starship launch tower from its unoccupied concrete base to its final height of ~145 meters (~475 ft) in about two months flat. While SpaceX will have to slalom its way around Pad 39A’s busy launch manifest, there’s no reason to believe that Starship’s first Florida launch tower won’t be stacked at least as quickly.
Aside from the arrival of crane parts, SpaceX has also made great progress on the Starship launch site itself. In the last few weeks, the company appears to have completed several significant concrete pours on the tower base. SpaceX has also installed all six of the pedestal-like orbital launch mount’s legs after months of foundation work. Elsewhere at Cape Canaveral, a different team has made excellent progress assembling the massive donut-like platform that will sit on top of those legs. Due to its extreme weight (possibly around 300 metric tons, per Elon Musk’s comments on the Starbase mount), the same LR 11350 crane will also be needed for that major installation milestone.

Plenty of parts are still missing, of course. Four tower sections still need to be assembled. Starship’s first Florida launch tower will need its own set of two ‘chopstick’ arms for lifting and (maybe) catching Starship and Super Heavy, as well as a third swinging quick-disconnect arm to connect Starship to ground systems. Aside from delivering several new tanks, SpaceX has also made no apparent progress on adding a massive methane propellant farm to Pad 39A, and it’s possible that the pad’s oxygen farm will also need to be expanded. Propellant storage has proven to be a major headache for SpaceX at Starbase.
Nonetheless, SpaceX is making great progress on most of the most difficult parts of Starship’s first Florida launch site, and there’s a good chance that just like its launch mount, work on the pad’s tower arms is already underway somewhere offsite. A great deal of work remains to be done but SpaceX is still well on its way to launching Starships out of Kennedy Space Center in the not-too-distant future.
News
EVgo taps Tesla Superchargers for mass charging expansion
EVgo has tapped Tesla Superchargers for its most recent efforts to expand its charging presence in the United States, a move that seems logical based on the effectiveness of the automaker’s own infrastructure.
EVgo opened its first Supercharger site in Illinois, a 12-stall station near downtown Chicago at 3145 South Ashland Avenue in the Riverside Square & River’s Edge center, right beside a grocery store. This marks the start of the company’s plan to deploy hundreds of Supercharger stalls across the United States, primarily at grocery-anchored Regency Centers properties where drivers can shop, eat, or run errands while they charge.
We’ve opened our first EVgo Supercharger location in Illinois, marking the start of our plan to add hundreds of Supercharger stalls across the U.S.
Designed for both NACS and CCS vehicles with Magic Dock technology, these new sites help make fast charging more accessible and convenient for all EV drivers. Learn more: https://t.co/V92t5FDryQ
— EVgo Fast Charging Network (@evgonetwork) November 5, 2026
The new location uses Tesla’s Magic Dock technology so both NACS and CCS vehicles can plug in natively without drivers needing to carry their own adapters. Peak power reaches 325 kW at this site, with pricing set between $0.25 and $0.35 per kWh depending on the hour—the same rate for Tesla and non-Tesla drivers.
The stalls also appear in Tesla’s in-car navigation and Trip Planner, making them easy for Tesla owners to find and route to. Illinois has seen EV registrations rise nearly 60 percent over the past two years, and EVgo’s broader network has experienced more than 700 percent growth in charging demand over three years, so the timing fits the market’s trajectory.
Choosing Tesla hardware through the Supercharger for Business program turns out to have been a smart, practical move.
Tesla’s V4 stalls and cabinets deliver high, reliable power with a proven track record of strong uptime, while Magic Dock delivers true dual-standard compatibility in one package. Because the sites show up in Tesla’s navigation tools, EVgo instantly gains visibility among millions of existing Tesla drivers, which should raise utilization and help the company double its addressable market as more vehicles adopt NACS. EVgo still owns the stations and sets pricing, yet benefits from Tesla’s established hardware, longer cables, and operational support.
The result is faster, lower-risk infrastructure expansion that serves every EV driver—Tesla or otherwise—with convenient, high-power charging at everyday retail locations. For drivers, that means fewer adapters, more predictable stops, and a denser network just as electric vehicles become everyday transportation.
News
Tesla Giga Texas reportedly moves to 24/7 production
Tesla’s Austin Gigafactory is reportedly shifting to round-the-clock vehicle production through the end of 2026, according to longtime drone observer Joe Tegtmeyer.
In his November 2 update, Tegtmeyer, widely regarded as one of the most reliable independent sources on Giga Texas activity (we call him the Drone GOAT), stated that the plant has added a night shift, creating two 12-hour production shifts.
Tegtmeyer said in his video:
“Now, I do have some interesting news about that when it comes to the production schedule here at Giga Texas, and things are actually looking pretty good, especially when you think about what the demand is and the delivery numbers that they’re looking for and what they’re expecting. So, normally they have shifts Monday through Friday. It’s a day shift and it’s about 10 hours long or so, give or take. But now they’re on day and night shifts and they’re going to 12-hour days. So they’re going to be adding or they have another shift. They have 12 hours for both of them. In addition to that, the typical downtime that we’re going to be seeing around the holidays, specifically Thanksgiving and Christmas to the New Year time frame is actually changed. And we’re not going to see those big several day events where there is no production. At least that’s what the plan is right now. So, it’s really a great sign, I think, when we consider what they’ve done in the past and what production and the deliveries have been so far. So, maybe it’s shaping up to be a really strong quarter.”
Previously, General Assembly typically operated on a single roughly 10-hour day shift, Monday through Thursday or Friday. The new arrangement keeps General Assembly on its Monday-to-Thursday schedule while adding overnight capacity, and most other areas of the factory continue working the full week with some weekend activity.
Notably, the plant is also forgoing the multi-day shutdowns around Thanksgiving and the Christmas–New Year period that have occurred in prior years
Giga Texas currently builds the Model Y, the larger Model Y L, the Cybertruck, and the Cybercab robotaxi. Tesla has not confirmed the shift change or specified which lines will receive the extra output. Recent comments suggest Cybercab production has been constrained by the pace at which the Robotaxi fleet can absorb new vehicles, making the Model Y and Model Y L the more likely beneficiaries as the company works through order backlogs.
Tegtmeyer’s November 2 footage and commentary also highlighted broader site progress. Cortex 2 continues to expand, with additional compute coming online, a roughly 25 percent lengthening of the structure on the north end, and work on a third cooling plant.
The Boring Company tunnel site showed increased activity in the large launch pit, while the Advanced Technology Chip Fab (a SpaceX–Tesla joint R&D facility) continued steel superstructure and heavy truss installation, along with concrete pours.
The reported capacity increase arrives as Tesla aims for a strong fourth quarter following solid third-quarter results. While unconfirmed by the company, the information aligns with Tegtmeyer’s consistent track record of accurate on-site observations.
If Tesla makes the decision to sustain the all-day production plans, the dual 12-hour shifts would meaningfully raise weekly output potential at one of Tesla’s most important manufacturing hubs.
News
Tesla opens new “Cybaer” Engineering Center in Berlin
Tesla opened its Berlin Engineering Center, uniting four sites and 30 labs near Giga Berlin.
Tesla has opened a new engineering hub in Berlin, putting the teams that design and test its European parts about 30 minutes from the factory that builds them.
The Berlin Tesla Engineering Center, or BTEC, opened Wednesday in the Köpenick district. Tesla Europe said on X that the project went from permit to operational in under a year and consolidates four engineering sites and 30 labs onto a single campus. It is the company’s third hub of this kind, after Fremont and Shanghai.
“We’re combining materials, powertrain, vehicle engineering & validation under one roof, enabling a short feedback loop between development & ramp,” Tesla Europe wrote.
Berlin Tesla Engineering Center opens today From permit to operational in under a year, it brings 4 engineering sites onto 1 campus w/ 30 different labs in Köpenick, 30 minutes from Giga Berlin With our 3rd hub of this kind after Fremont & Shanghai, we’re combining materials, powertrain, vehicle engineering & validation under one roof – enabling a short feedback loop between development & ramp — Tesla Europe, Middle East & Africa (@teslaeurope) November 4, 2026
Tesla converted the former production halls of a cable factory for the site. About 250 engineers and technicians are starting there, most of them relocated from existing Tesla facilities such as Tilburg in the Netherlands. Tesla has already applied for approval of a second phase that would take the headcount to roughly 500, and it put the total investment at €100 million.
The labs cover battery cells, motors, materials and complete vehicles, and a large hall is set aside for safety testing of components, including airbags. During the opening, staff demonstrated a pedestrian leg impact test on the front of a Tesla using a catapult rig, Tagesspiegel reported. The center’s logo is a cubist Berlin bear that employees call the “Cybaer.”
Tesla said its Berlin design and engineering teams already contributed to the Model Y, Semi and Roadster, and that the work continues at BTEC. The center will handle technical problem solving for Giga Berlin in Grünheide while also developing and validating parts for vehicles built in China and the United States.
“We came here to stay,” BTEC head Brückner told dpa. “We serve all of Europe via Gigafactory Berlin-Brandenburg.” He said a site close to the plant was a priority, and that the old industrial building allowed Tesla to move quickly.
That proximity matters more now that Giga Berlin is growing again. In June, Tesla said it would raise Model Y output at the plant to 7,500 vehicles per week and hire 1,000 more workers after a record first quarter of more than 61,000 units. The factory recently built 7,000 Model Ys in a single week for the first time. Tesla also more than doubled the planned 4680 cell capacity at the site to 18 GWh per year in May, and has talked about eventually taking Grünheide to one million vehicles annually.
Sales are giving Tesla reason to invest. KBA data released the same day showed Tesla’s German registrations nearly quadrupled year over year in October to 2,932 units, bringing the total for the first ten months of 2026 to 47,742.