Tesla Giga Berlin’s 4680 supply won’t start in Germany, and it was never supposed to
Tesla’s plans for the initial battery needs and efforts at Giga Berlin were answered in late 2020 by the automaker during the Q3 Earnings Call. While things tend to change on a somewhat regular basis as far as plans for something as large as a vehicle manufacturing plant, Tesla knew that its initial battery fulfillment plans likely wouldn’t come from the planned Giga Berlin 4680 cell production lines. Instead, Tesla will rely on its Kato Road facility in Northern California, where the development and manufacturing of a new, revolutionary electric vehicle battery is taking place. Tesla also plans to utilize strong relationships with its battery cell manufacturers to solve supply concerns during Giga Berlin’s early production dates.
Concerns regarding Tesla’s planned timeline for Giga Berlin have arisen over the past several days, especially after a German media outlet said that CEO Elon Musk was extending the beginning of the German plant’s EV production efforts to January 2022. While the Giga Berlin timeline remains uncertain as far as the exact starting date, those close to the situation, including Brandenburg Economic Minister Jörg Steinbach, told Teslarati yesterday that production should begin in late Summer or early Fall 2021.
EXCLUSIVE: Tesla Giga Berlin isn’t facing a 6-month delay: German Minister
The concerns about Tesla Giga Berlin’s initial production date started to appear around the same time that reports began to surface about Tesla adding the 4680 battery manufacturing unit plans to its application. German regulators take a deliberate and somewhat extended time for large projects, as so many different factors are considered before anything is given ultimate approval. Some indicated that this extensive regulatory process would delay the production efforts altogether. Still, local sources in Germany have clarified that this only prolongs the project altogether and doesn’t have much of an effect on the start of production. The project will just take longer to complete considering Tesla added another element to the Giga Berlin offensive.
As previously mentioned, the addition of the 4680 line to the application likely caused confusion over whether the Tesla Giga Berlin production lines would activate on time. 4680 production at Berlin will not begin before or at the same time as Tesla’s vehicle production at the German plant. However, Tesla’s plans were never to have the Berlin 4680 lines handle the initial vehicle production at the plant. Tesla originally planned for the Kato Road 4680 lines to supply Giga Berlin with cells when they are available.
Drew Baglino, Tesla’s Senior Vice President of Powertrain and Energy Engineering, said during the Q3 2020 Earnings Call:
“We will incorporate 4680 design solutions into many applications in time across both energy and vehicle, and we can use our pilot production facility in Fremont to support the new factory in Berlin as it ramps.”
Additionally, Tesla’s battery suppliers are being called upon to assist in the initial efforts at Giga Berlin.
Musk announced during the most recent Q1 2021 Earnings Call that Tesla is about 12-18 months away from volume production of 4680 cells. While Tesla may be slightly behind schedule regarding the production of the new 4680 battery, there is no indication that it will delay Giga Berlin’s production altogether. In fact, Musk also acknowledged that its suppliers, who Tesla shares “very strong partnerships” with would be called upon to supply cells “as much as they possibly can.”
Musk said:
“…It appears as though we’re about 12 — probably not more than 18 months away from volume production of the 4680. Now at the same time, we are actually trying to have our cell supply of partners ramp up their supply as much as possible. So this is not something that is to the exclusion of suppliers. It is in conjunction with suppliers. So we want to be super clear about that. This is not about replacing suppliers. It is about supplementing the suppliers. So…and we have a very strong partnership with CATL, with Panasonic and LG. And we would…our request to our strategic partners for cell supply is, please make us…please supply us with as much as you possibly can. Provided the price is affordable, we will buy everything that they can make.”
This includes CATL, a Chinese battery producer who manufactures LFP cells for the Standard Range+ Model 3 at Giga Shanghai. CATL began the construction of a cell manufacturing facility in Germany in 2019. LG Chem also started the construction of an EV battery cell manufacturing facility in Poland in 2017, which could be used to supplement Tesla’s battery efforts in Germany. These suppliers have both assisted Tesla with cells in the past, and these companies will likely supplement Tesla’s needs at Giga Berlin, as Musk requested during the Q1 2021 Earnings Call.
Tesla has been aware that the 4680 lines in Berlin will not take care of the initial production phases at the factory. Instead, it will rely on suppliers and its Kato Road 4680 lines in the United States to take care of the first months of production at Giga Berlin.
News
Tesla opens Supercharging Network to other EVs in new country
Tesla’s Supercharging infrastructure is the most robust in the world, and it has done a wonderful job of keeping things up and running for the millions of owners out there. As it expanded access to non-Tesla EVs a couple years back, it has still managed to keep things pretty steady, although the need for more charging is apparent.
Tesla has started opening its Supercharging Network, which is the most expansive in the world, to other EVs in a new country for the first time.
After expanding its Supercharging offerings to other car companies in the United States a few years ago, Tesla is still making the move in other markets, as it aims to make EV ownership easier for everyone, regardless of what manufacturer a consumer chose to purchase from.
Tesla’s Supercharging infrastructure is the most robust in the world, and it has done a wonderful job of keeping things up and running for the millions of owners out there. As it expanded access to non-Tesla EVs a couple years back, it has still managed to keep things pretty steady, although the need for more charging is apparent.
Tesla just added a cool new feature for leaving your charger at home or even leaving the Supercharger pic.twitter.com/iw0SDrWuX6
— TESLARATI (@Teslarati) March 10, 2026
Now, Tesla is expanding access to the Supercharger Network to non-Tesla EVs in Malaysia. The automaker just opened up a charging stie at the Pavilion KL Mall in Kuala Lumpur to non-Tesla owners, giving them eight additional Superchargers to utilize with a charging speed of up to 250 kW.
Tesla is also opening up the four-Supercharger site in Shah Alam, a four-Supercharger site at the IOI City Mall, and a six-Supercharger site in Gamuda Cove Township.
Electrive first reported the opening of these Superchargers in Malaysia.
The initiative from Tesla helps make EV ownership much simpler for those who only have access to third-party charging solutions or at-home charging. While at-home charging is the most advantageous, it is not an end-all solution as every driver will eventually need to grab some range on the road.
Tesla has been offering its Superchargers to non-Tesla EVs in the United States since 2024, as Ford became the first company to gain access to the massive network early that year when CEO Elon Musk and Ford frontman Jim Farley announced it together. Since then, Tesla has offered its chargers to nearly every EV maker, as companies like Rivian and Lucid, and even legacy car companies like General Motors have gained access.
It’s best for everyone to have the ability to use Tesla Superchargers, but there are of course some growing pains.
Charging cables are built to cater to Tesla owners, so pull-in Superchargers are most advantageous for non-Tesla EVs currently, but the company’s V4 Superchargers, which are not as plentiful in the U.S. quite yet, do enable easier reach for those vehicles.
News
Tesla Semi expands pilot program to Texas logistics firm: here’s what they said
Mone said the Tesla Semi it put into its fleet for this test recorded 1.64 kWh per mile efficiency, beating Tesla’s official 1.7 kWh per mile target and delivering a massive leap over conventional diesel trucks.
Tesla has expanded its Semi pilot program to a new region, as it has made it to Texas to be tested by logistics from Mone Transport. With the Semi entering production this year, Tesla is getting even more valuable data regarding the vehicle and its efficiency, which will help companies cut expenditures.
Mone Transport operates in Texas and on the Southern border, and it specializes in cross-border U.S.-Mexico freight operations. After completing some rigorous testing, Mone shared public results, which stand out when compared to efficiency metrics offered by diesel vehicles.
“Mone Transport recently had the opportunity to put the Tesla Semi to the test, and we’re thrilled with the results! Over 4,700 miles of operations at 1.64 kWh/mile in our Texas operation. We’re committed to providing zero-emission transportation to our customers!” the company said in a post on X.
🚨 Mone Transport just recorded an extremely impressive Tesla Semi test:
1.64 kWh per mile over 4,700 miles! https://t.co/xwS2dDeomP pic.twitter.com/oLZHoQgXsu
— TESLARATI (@Teslarati) March 10, 2026
Mone said the Tesla Semi it put into its fleet for this test recorded 1.64 kWh per mile efficiency, beating Tesla’s official 1.7 kWh per mile target and delivering a massive leap over conventional diesel trucks.
Comparable Class 8 diesel semis, typically achieving 6-7 miles per gallon, consume roughly 5.5 kWh per mile in energy-equivalent terms, meaning the Semi uses three to four times less energy while also producing zero tailpipe emissions.
Tesla Semi undergoes major redesign as dedicated factory preps for deliveries
The performance of the Tesla Semi in Mone Transport’s testing aligns with data from other participants in the pilot program. ArcBest’s ABF Freight Division logged 4,494 miles over three weeks in 2025, averaging 1.55 kWh per mile across varied routes, including a grueling 7,200-foot Donner Pass climb. The truck “generally matched the performance of its diesel counterparts,” the carrier said.
PepsiCo, which operates the largest known Semi fleet, recorded 1.7 kWh per mile in North American Council for Freight Efficiency testing. Additional pilots showed similar gains: DHL hit 1.72 kWh per mile, and Saia achieved 1.73 kWh per mile.
These metrics underscore the Semi’s ability to slash operating costs through superior efficiency, lower maintenance, and zero-emission operation. As charging infrastructure scales and production ramps toward 2026 targets, participants like Mone Transport are proving electric semis can seamlessly integrate into freight networks, accelerating the industry’s shift to sustainable, high-performance trucking.
Tesla continues to prep for a more widespread presence of the Semi in the coming months as it recently launched the first public Semi Megacharger site in Los Angeles. It is working on building out infrastructure for regional runs on the West Coast initially, with plans to expand this to the other end of the country in the coming years.
Elon Musk
SpaceX weighs Nasdaq listing as company explores early index entry: report
The company is reportedly seeking early inclusion in the Nasdaq-100 index.
Elon Musk’s SpaceX is reportedly leaning toward listing its shares on the Nasdaq for a potential initial public offering (IPO) that could become the largest in history.
As per a recent report, the company is reportedly seeking early inclusion in the Nasdaq-100 index. The update was reported by Reuters, citing people familiar with the matter.
According to the publication, SpaceX is considering Nasdaq as the venue for its eventual IPO, though the New York Stock Exchange is also competing for the listing. Neither exchange has reportedly been informed of a final decision.
Reuters has previously reported that SpaceX could pursue an IPO as early as June, though the company’s plans could still change.
One of the publication’s sources also suggested that SpaceX is targeting a valuation of about $1.75 trillion for its IPO. At that level, the company would rank among the largest publicly traded firms in the United States by market capitalization.
Nasdaq has proposed a rule change that could accelerate the inclusion of newly listed megacap companies into the Nasdaq-100 index.
Under the proposed “Fast Entry” rule, a newly listed company could qualify for the index in less than a month if its market capitalization ranks among the top 40 companies already included in the Nasdaq-100.
If SpaceX is successful in achieving its target valuation of $1.75 trillion, it would become the sixth-largest company by market value in the United States, at least based on recent share prices.
Newly listed companies typically have to wait up to a year before becoming eligible for major indexes such as the Nasdaq-100 or S&P 500.
Inclusion in a major index can significantly broaden a company’s shareholder base because many institutional investors purchase shares through index-tracking funds.
According to Reuters, Nasdaq’s proposed fast-track rule is partly intended to attract highly valued private companies such as SpaceX, OpenAI, and Anthropic to list on the exchange.