Tesla Giga Berlin August update: Body In White begins, Drive Unit nears completion

Credit: YouTube | FlyBrandenburg

Published

on

Tesla Giga Berlin’s construction continues to move along at a rapid pace, and the first beams of the “Body in White” portion of the facility have been erected as of this morning.

Body in White is the stage in automotive manufacturing where the frame of a car body is joined together. It is often the point where the final contours of a vehicle’s body are worked out in preparation for the stamping process.

In Berlin, this portion of Tesla’s Giga Berlin production plant is being built and is accelerating nicely ahead of the company’s planned initial production runs in July 2021.

Photos from @gigafactory_4 on Twitter show the progress that is being made on the Body in White building, with vertical beams being installed into the foundation of the property.

Vertical beams of the Body in White structure at Giga Berlin. (Credit: @gigafactory_4 on Twitter)

The Body in White building is where most of the initial manufacturing process will occur. When the Model Y begins production at the facility next year, the vehicle’s chassis will be built in this structure with a simplified manufacturing process, according to Tesla CEO Elon Musk.

Musk detailed the Berlin Model Y’s details during the company’s Q2 2020 Earnings Call, where he said that the design of the Germany-built crossover would be modified to increase manufacturing ability.

Advertisement

“And we’re really changing the design of the car in order to make it more manufacturable,” Musk said. “The fundamental architecture of Model Y will be different in Berlin, it may look the same, but the internals will be quite different and fundamentally more efficient architecturally than what we’ve done to date.”

Giga Berlin’s progress is accelerating quickly, thanks to the construction methods that are being used.

Tesla’s contracted construction crews on the site are utilizing prefabricated methods of building to decrease the amount of time it takes to put the structures together. The prefabricated process requires some portions of buildings to be put together at a separate location. These are then transported to the site and installed into the appropriate area.

The Drive Unit facility is the building that has the most progress done to it thus far. The Northern wall of the DU building is nearly complete after the first portions of the partition were erected on August 5, just six days ago.

The Northern wall of the Drive Unit is nearly completed. (Credit: @gigafactory_4 on Twitter)

Tesla expects Model Y production to begin at the plant next July. Despite the hot temperatures in Berlin, construction crews are moving along quickly in preparation for a massive push of Tesla’s electric vehicles in Europe next year.

A video of the Giga Berlin site is available below courtesy of FlyBrandenburg.

Advertisement

https://youtu.be/a3x0RdXd1pw

 

Joey has been a journalist covering electric mobility at TESLARATI since August 2019. In his spare time, Joey is playing golf, watching MMA, or cheering on any of his favorite sports teams, including the Baltimore Ravens and Orioles, Miami Heat, Washington Capitals, and Penn State Nittany Lions. You can get in touch with joey at joey@teslarati.com. He is also on X @KlenderJoey. If you're looking for great Tesla accessories, check out shop.teslarati.com

Advertisement
Comments

Elon Musk

SpaceX Starship just nailed something it’s never done before

SpaceX’s Starship flew successfully Friday, landing both stages and deploying its first Starlink V3 satellites.

Published

on

By

Starship’s thirteenth test flight delivered exactly what SpaceX needed with a clean liftoff, two successful stage recoveries, and the first real payload the vehicle has ever carried to space. Booster 20 and Ship 40 lifted off at 5:51 p.m. CT from Starbase, and by the time the mission wrapped roughly an hour later, both halves of the rocket had done exactly what they were supposed to do.

Booster 20 separated from Ship 40 a few minutes into the flight and stuck a controlled splashdown in the Gulf of Mexico about six minutes after liftoff. That is a meaningful turnaround from Flight 12 in May, when the booster lost several engines during its boostback burn before a hard water landing attempt.


Starship 40’s performance was arguably the bigger win. The vehicle deployed the first 20 operational Starlink V3 satellites Starship has ever carried, then flew a suborbital arc to a landing in the Indian Ocean that SpaceX commentator Dan Huot called the company’s softest splashdown yet. “This is a dream scenario for this team that’s trying to get this heat shield data,” Huot said on the live broadcast, according to Space.com’s live coverage. “I’m a little over the moon right now. Wow. Lucky number 13.”

Unlike the mass simulators SpaceX flew on Flight 12, these were production Starlink V3 satellites, meant to extend solar arrays and antennas and attempt to link with the broader constellation before reentering minutes later. Getting real hardware through a full deploy sequence on only the second flight of the V3 generation keeps Starship on schedule for the payload work NASA is counting on for future Artemis lunar landings.

Advertisement

— TESLARATI (@Teslarati) July 25, 2026

The flight also arrives at a moment when SpaceX needed a win. SPCX has traded below its $135 IPO price since mid-July, as Teslarati reported when the mission slipped to Friday, and short interest has climbed to roughly a third of the tradable float. A clean flight will not fix a balance sheet, but it does answer the one question SpaceX absolutely needed answered this week: whether the fixes made after the July 16 abort would hold up under real flight conditions. They did, on both stages, on the first try after the redesign.

SpaceX has not set a target date for Flight 14, though the company has said it wants to push toward an orbital attempt on the next mission. After Friday, that goal looks a lot more within reach.

Advertisement
Continue Reading

News

Tesla’s Supercharger Diner probably just secured more locations

Published

on

tesla diner
Credit: Tesla

Tesla’s Supercharger Diner in Los Angeles dominated the company’s global usage rankings after just one year, proving the concept is more than just a one-off novelty location that will fade away.

The performance could incite the company to build more locations, something that CEO Elon Musk has hinted at for some time.

Tesla’s Supercharger Diner delivered 21.2 GWh of energy in its first year of operation, the company’s head of Charging, Max de Zegher, revealed on X. Of the top 10 most utilized Supercharger locations in Tesla’s global infrastructure, the Diner in Los Angeles was the most used by drivers, and it wasn’t particularly close:

On its launch day one year ago, nobody was too sure what the Tesla Diner would be about. It seemed like an interesting concept, and considering it had been in the works for years, it was a highly anticipated launch that many were looking forward to.

Based on its success, we could see additional Diners with Superchargers built throughout the United States, and potentially beyond. Musk has said on several occasions that the company would be willing to bring the Diner idea to more markets.

Tesla makes major change at Supercharger Diner amid epic demand

Advertisement

Of the markets that Musk has mentioned, both Palo Alto and Austin have come to be perceived as ideal selections. However, there are no concrete plans as of now to build new Supercharger Diners anywhere; the location on Santa Monica Boulevard will remain the exclusive spot to pick up Tesla-inspired eats, at least for the time being.

Continue Reading

Investor's Corner

Tesla short sellers win big after shares fall after earnings

Published

on

A red Tesla Roadster driving around a turn
(Credit: Tesla)

Tesla short sellers won big following the company’s massive fall on Wall Street after it reported subpar Earnings on Wednesday.

Tesla short sellers collected about $4.12 billion in single-day profits on Thursday, according to BloombergShares fell as much as 15 percent during Thursday’s session. It closed as one of the worst days for Tesla on Wall Street in the past three years.

Investors sold off the stock after Tesla said it would aggressively direct its spending toward AI and its Optimus robot project. The company had record revenues, which were driven by one of the strongest quarters in terms of vehicle deliveries in company history.

Advertisement

However, it missed EPS estimates by reporting just $0.33, a far cry from the $0.53 analysts expected.

S3 Partners reported that about 3 percent of Tesla’s outstanding stock is sold short. Managing Director at S3, Ihor Dusaniwsky, provided the short seller’s potential profit, as well as another figure: shorts have likely had paper gains of $8.92 billion this year, as Tesla shares are down 30 percent in 2026.

Tesla (TSLA) Q2 2026 earnings results: miss on EPS, beat on revenue

Tesla has burned short sellers many times in the past, but the company’s latest Earnings Call was a chance for those skeptics to taste some payback. Although the company gave some very transparent information regarding future projects, the rollout of Robotaxi, Optimus, and Semi, many investors took their profits on Thursday.

Notable short sellers like Michael Burry have been transparent about their skepticism around Tesla shares. Burry just revealed three weeks ago that he had opened up a new short on the stock, stating he shorted Tesla shares at $416.22. “Happy it jumped back to this level,” he said in a blog post.

Advertisement

At the time of publication, Tesla shares were down about 3 percent and the stock was trading at $309.92.

Continue Reading