Tesla’s 4680 battery cell pilot production line hits 70-80% yield: report

Credit: Tesla Inc.

Published

on

Tesla has a number of programs that have the potential to change markets, and one of these is arguably the 4680 cells. Created using a dry electrode process and optimized for price and efficiency, the 4680 batteries could very well be the key to Tesla’s possible invasion of the mainstream auto and energy market. If Tesla pulls off its 4680 production ramp, its place at the summit of the sustainable energy market would be all but ensured. 

Unfortunately, Tesla’s publicly disclosed target for the 4680 cells’ production ramp appears to have been made on “Elon Time.” This means that during Battery Day last year, Tesla’s target of hitting a capacity of 10 GWh by late September 2021 included some optimistic assumptions. Similar to other projects like Elon Musk’s Alien Dreadnaught factory, however, the pilot production of the 4680 cells have met some challenges. 

Credit: Tesla Inc.

Tesla admitted to these difficulties during the Q2 2021 earnings call, when Elon Musk explained that one of the main challenges in the 4680 cell production ramp was related to the batteries’ calendaring, or the process when the dry cathode material is squashed to a particular height. Partly due to the use of nickel in the 4680 cells, which are extremely hard, some of the calendar rolls end up being dented. 

This was an issue that presented itself only in the pilot 4680 line, not during the bench and lab stages. Tesla Senior Vice President of Powertrain and Energy Engineering Drew Baglino, however, emphasized that the challenges in the Kato Road facility are an engineering problem and not a science issue. This meant that with enough work and optimization, Tesla should be able to address the calendaring issues of the dry battery cells. 

Credit: evmadrid/Instagram

Citing sources familiar with the matter, Tesla investor and host of YouTube’s Hyperchange channel Galileo Russell recently shared some details suggesting that Tesla may have hit some breakthroughs with the production of the 4680 cells. As per the Tesla investor, the production yield of the 4680 cells has reportedly risen to about 70-80%, up from just about 20% last year. This means that a decreasing portion of the 4680 cells produced today are seeing issues, and Tesla’s pilot battery line at Kato Road is starting to close in on the acceptable yields of factories like Giga Nevada. 

While the delays in the 4680 cells appear to have affected the rollout of products like the Cybertruck and the Semi, it is starting to become evident that Tesla is about to hit some respectable battery output from its pilot line in California. Fortunately, the company has already initiated some contingencies that address the 4680 cells’ delays. The production of the Model Y in Giga Berlin and Giga Texas would be launched with 2170 battery packs, for example, at least until the 4680 cells are available. 

Watch Hyperchange‘s feature on Tesla’s 4680 battery production challenges in the video below.  

Don’t hesitate to contact us with news tips. Just send a message to tips@teslarati.com to give us a heads up. 

Advertisement
-

Simon is an experienced automotive reporter with a passion for electric cars and clean energy. Fascinated by the world envisioned by Elon Musk, he hopes to make it to Mars (at least as a tourist) someday. For stories or tips--or even to just say a simple hello--send a message to his email, simon@teslarati.com or his handle on X, @ResidentSponge.

Advertisement
Comments

News

Tesla has a ‘no human contact’ approach for Semi production

Published

on

Tesla is advancing a fully automated pipeline for the 4680 battery cells used in its all-electric Semi, spanning production from Giga Texas through shipment and direct consumption on the line at the new dedicated Semi Factory in Sparks, Nevada.

The approach was outlined by Tesla at its September 24 Semi Handover event, which launched high-volume production at its new 1.8-million-square-foot plant in Nevada, which sits adjacent to Gigafactory Nevada and is designed for an annual production rate of 50,000 trucks per year.

After years of pilot builds and what was a four-year-long redesign of the truck, Tesla moved the Semi from 2170 batteries to its in-house 4680 cells, which are made in Austin. The change cuts battery mass and total energy while holding range, a key step in making volume production a realistic possibility.

Cells will leave Giga Texas in trailers, and at the Nevada Semi plant, Tesla intends for a dedicated line to unload those trailers automatically, station the cells, and feed them straight into pack and vehicle assembly.

Both Lars Moravy, Tesla’s VP of Vehicle Engineering, and Dan Priestley, the Head of Tesla’s Semi program, described the goal as a “zero human touch point” from the moment the trailer arrives in Texas until a finished Semi drives off the production line in Nevada.

The unloading system that Moravy and Priestley described is just one piece of a much broader automation push. The plant uses what Tesla calls the highest-capacity electric monorail conveyance in vehicle manufacturing, carrying frames-in-white simultaneously. Powder-coating replaces conventional paint, and many processes that would normally require operators have been designed out.

Tesla has repeatedly said that “the best part is no part,” and the cell-handling plan extends that philosophy from the cell factory floor in Texas all the way to final assembly in Nevada.

If executed as described, the closed-loop flow would reduce labor, handling damage, and inventory buffers while tightening quality control on a component that represents a large share of the truck’s cost and weight. It also shortens the physical and organizational distance between two factories separated by more than 1,200 miles. The Semi itself now shares a bar-wound stator and other components with the Cybertruck, further linking Tesla’s passenger and commercial production systems.

High-volume output is expected to ramp gradually after the first trucks left the new line in April 2026. Early customers include PepsiCo, DHL, and U.S. Foods. Whether the automated trailer-to-line process reaches the promised zero-touch standard will be visible in the coming months as production scales. For Tesla, the Semi factory is another test of how far it can push “the machine that builds the machine” across sites.

Continue Reading

Elon Musk

Elon Musk’s AI Grok Bot can now handle banking while your Tesla FSD handles the road

Elon Musk says Grok Bot can manage your finances through linked bank and investment accounts.

Published

on

By

Concept of SuperGrok Bot handling banking in a Tesla via Grok
Concept of SuperGrok Bot handling banking in a Tesla via Grok

Grok Bot now wants access to your wallet, with SpaceXAI rolling out a new Finance integration for its agent platform that lets users link bank, credit card and investment accounts thereby letting their Bots help manage spending, investments and more. Elon Musk amplified the announcement on X with a short endorsement, “Grok Bot can manage your finances.”

The feature builds on two earlier steps. In early September, Grok gained the ability to answer questions about spending, savings, investments and cash flow using accounts connected through Plaid, starting with users in the U.S. Before that, on August 28, SpaceXAI let Grok Bot buy things online through Link, with users approving every spend request and the Bot receiving a single use card for each payment.

Musk has already shown how far he wants users to push it. In late August, when Tesla investor account Teslaconomics said he was weighing whether to give Grok Bot access to his bank accounts, Musk replied, “Try it out. If Grok Bot messes up, we will make you whole.” That promise goes beyond SpaceXAI’s consumer terms, which make users responsible for what their agents do and generally cap the company’s liability at the greater of fees paid or $100. SpaceXAI’s own documentation recommends requiring approval for purchases and financial transfers.

For Tesla owners, the update lands five days after Tesla brought Grok Bot into its vehicles, letting drivers hand off errands by voice while FSD (Supervised) handles the road. Bot access inside the car is currently limited to SuperGrok Heavy subscribers, though Connectors are open to anyone signed into Grok. With Finance linked, a driver could ask for a spending summary or a check on upcoming bills during the commute.

Grok’s role in the car has grown quickly since Tesla’s Summer Update let it control cabin features by voice. We have been using Grok Bot in our own Tesla for several weeks, and here’s how our latest test went.

Advertisement
-
Continue Reading

Elon Musk

SpaceX just got the green light Starship has waited years for

The FAA has cleared Starship Flight 14, setting up SpaceX’s first orbital attempt on Monday.

Published

on

By

SpaceX has cleared the last regulatory hurdle standing between Starship and its first trip to orbit. The Federal Aviation Administration issued the launch license for Starship Flight 14 late Saturday, keeping the mission on track for liftoff Monday, September 28, from Pad 2 at Starbase, Texas.

The 75 minute launch window opens at 7:15 a.m. Central, and Boca Chica Beach closures are also scheduled for September 29 and 30 as backup dates. This will be Starship’s first revenue generating mission.

The license was the missing piece after SpaceX completed a full wet dress rehearsal with Booster 21 and Ship 41 on September 24. At the time, the company said the flight remained on track pending regulatory approval. Because Flight 14 flies an orbital profile, the FAA had to sign off on a modified license that met its safety, payload and financial responsibility requirements.

Observers combing through the new FAA paperwork also noticed that lightning no longer appears among Starship’s listed launch hazards. If that holds, it matters more for where Starship is headed than for Monday’s attempt. Florida and Louisiana, home to LC-39A and the planned Starbase Louisiana site, see some of the most frequent lightning in the United States.

SpaceX tells the FCC that Starship Flight 14 is going to orbit

Flight 14 is the mission SpaceX has been building toward for months. Ship 41 will carry 26 Starlink V3 satellites, the first operational V3 units to be deployed, and attempt roughly six orbits at about 275 kilometers over a flight lasting just under 10 hours. SpaceX says the ship will only perform its orbital insertion burn after flight controllers confirm enough hardware redundancy remains for the deorbit burn at the end of the mission. Ship 41 is targeting a splashdown in the Pacific west of Chile, while Super Heavy will return to the Gulf of Mexico.

The date carries some symbolism as well. A Monday launch would come 10 years and one day after Elon Musk first presented the Interplanetary Transport System, the design that became Starship, at the International Astronautical Congress in Guadalajara, Mexico.

Advertisement
-

SpaceX has not announced what comes next, but air traffic planning slides reported this week, list Flight 15 no earlier than October 19 and a first Starship launch from LC-39A in Florida no earlier than October 30. Both dates depend on how Monday goes.

Continue Reading