News
SpaceX ‘tops off’ its South Texas Starship prototype with one final steel dome
On September 14th, South Texas SpaceX technicians lifted Starship Mk1’s third and final tank dome and began to attach it atop the prototype’s steel tank section, this time making use of a new method of integration.
This progress comes just two weeks before CEO Elon Musk is expected to present a detailed update on Starship’s newest design iteration. Musk is hopeful that – come his September 28th presentation – Starship Mk1 will be nearly complete and ready for its inaugural flight, a milestone that could come as early as October 13th according to Starship documents filed with the FCC.
This latest installation is likely either the last ring (or nearly so) to be stacked on top of Starship Mk1, paving the way for the eventual attachment of the spacecraft’s conical nose section and the fleshing out of its many internal subsystems and aerodynamic control surfaces. This particular milestone involved the attachment of Starship’s third and final tank bulkhead – in this case, the upper dome of the prototype’s liquid oxygen tank. Excluding hardware that might eventually be installed on the dome itself, this means that Starship Mk1’s tank and engine section has essentially been ‘topped off’.
As previously estimated by the author, this particular tank dome installation – the fifth completed by SpaceX’s Mk1 and Mk2 Starship teams – was done in a manner thus far unique. All previous installations have seen SpaceX technicians lower the domes – completed aside from one vertical weld for flexibility – inside the Starship’s cylindrical tank section. The steel domes are then carefully spot-welded to the side of the tank in their proper place – all while being supported by a large crane – before technicians can complete a seamless ring weld around their entire circumference.

This time around, SpaceX welded the upper tank dome to its companion ring section while both elements were still staged on the ground. Once the dome was completely welded to the steel ring and a dome cap was installed to seal off the top, the ring segment was craned atop Starhip Mk1 on September 14th. It’s possible that this was planned all along for each Starship’s third and final tank dome, but the way CEO Elon Musk has previously described SpaceX’s semi-competitive Mk1 and Mk2 builds suggests that it may instead be a new assembly strategy that evolved in just the last month or two.

Instead of having to do the work of fitting, attaching, and ring-welding the bulkhead to Starship’s tank section 50-100 feet above ground, with all the associated rigging, scaffolding, and challenges such a work environment demands, technicians were able to do the majority of that work at ground-level. This method seems to offload the added challenge of dome installation to the vertical ring installation process, effectively merging the two processes into one much simpler (and safer) feat.
The fact that Starship Mk1’s tank section has now been capped (aside from several small access ports) indicates that all large, plumbing-related components have been installed inside the steel prototype. Up next for Starship Mk1 is the installation of its landing legs/fins/wings (at least two of which have already arrived on-site), canards, and a variety of smaller additions like valves, thrusters, ground connection points, and much more.
Check out Teslarati’s Marketplace! We offer Tesla accessories, including for the Tesla Cybertruck and Tesla Model 3.
Elon Musk
NASA just gave SpaceX more crew missions because Boeing can’t certify
NASA has filed a procurement notice announcing its intent to add six post-certification missions to SpaceX’s existing Commercial Crew Transportation Capability contract. The agency said it would order up to three of those missions immediately upon adding them to the contract, with the remaining three available as needed through the end of the International Space Station’s planned operations in 2030.
The reason for the expansion is straightforward. NASA cited recently shortened ISS mission durations, technical issues and schedule delays encountered by Boeing, the allocation of missions between Boeing and SpaceX, and the ongoing technical challenges of maintaining a reliable crew transportation capability as the driving factors behind the decision. Boeing’s CST-100 Starliner has still not been certified for crewed flights, and a cargo-only Starliner mission was not included on NASA’s most recent mission manifest. With Boeing effectively sidelined for the foreseeable future, SpaceX is the only American company capable of rotating crews to the station.
The history behind this contract tells the fuller story of how SpaceX got here. NASA originally awarded SpaceX its Commercial Crew contract in 2014 for $2.6 billion. In 2022 NASA modified the contract to add five missions covering Crew-10 through Crew-14, worth $1.436 billion, bringing the total contract value at that point to $4.9 billion. The recent May 18 filing by NASA extends that runway further, with Crew-12 currently docked at the station and Crew-13 assigned and targeting a mid-September 2026 launch.
According to a report by SpaceNews, NASA stated in its filing: “It is necessary to award additional PCMs to SpaceX given the recently shortened ISS mission durations, technical issues and schedule delays encountered by Boeing, the allocation of missions between Boeing and SpaceX, NASA’s projections for when an alternative crew transportation system may become available, and the ongoing technical challenges of maintaining a reliable capability for crewed flights to ISS.”
No dollar value for the new six missions has been publicly confirmed yet, but based on the 2022 precedent of roughly $287 million per mission, the new block could represent close to $1.7 billion in additional contract value. With SpaceX simultaneously preparing Starship as NASA’s Artemis lunar lander, filing its S-1 for a June IPO, and now absorbing more ISS crew rotation work, the company’s role as the primary contractor for American human spaceflight is no longer a matter of circumstance. It is NASA policy.
Energy
Zuckerberg’s Meta taps Musk’s Tesla for massive clean energy project
In a notable intersection of Big Tech powerhouses, Meta, led by Mark Zuckerberg, has partnered with Canadian energy infrastructure giant Enbridge on a significant renewable energy initiative that will rely on battery technology from Elon Musk’s Tesla.
The project, which was announced this week, marks another step in Meta’s aggressive push to power its expanding data center operations with clean energy, dispelling many of the complaints people have about them.
This new development is located near Cheyenne, Wyoming, and will feature a 365-megawatt (MW) solar farm paired with a 200 MW/1,600 megawatt-hour (MWh) battery energy storage system, also known as BESS. Tesla is providing the batteries for the project, valued at roughly $200 million.
The story was originally reported by Utility Dive.
This Wyoming project represents the first phase of Enbridge and Meta’s joint “Cowboy Project.” Once operational, it will deliver power to Meta’s regional data centers through Cheyenne Light, Fuel, and Power under Wyoming’s Large Power Contract Service tariff.
This tariff, originally developed in collaboration with Microsoft and Black Hills Energy, is designed specifically for large loads like data centers. It ensures that the renewable supply serves hyperscale customers without impacting retail electricity rates for other users.
The battery system will operate under a long-term tolling agreement, providing dispatchable capacity that enhances grid reliability. During periods of high demand, the utility can access the backup generation, addressing one of the key challenges of integrating large-scale renewables with the explosive growth of data center electricity demand driven by artificial intelligence.
This latest collaboration builds on prior joint efforts between Enbridge and Meta in Texas, including the 600 MW Clear Fork Solar, 152 MW Easter Wind, and 300 MW Cone Wind projects. Together with the Wyoming initiative, the companies have now partnered on roughly 1.6 gigawatts (GW) of combined solar, wind, and storage capacity.
The deal highlights the intensifying demand for reliable, low-carbon power from technology giants. Meta has committed to supporting its data center growth with renewable energy, joining peers like Microsoft and Google in seeking large-scale solutions. Enbridge’s Allen Capps described the project as “one of the larger utility-scale battery installations supporting U.S. data center operations and growth.”
The involvement of Tesla’s battery technology adds an intriguing layer, linking two of the world’s most prominent tech leaders—Zuckerberg and Musk—in the clean energy transition.
As data centers continue to drive unprecedented electricity load growth across the United States, projects like this one illustrate how hyperscalers are turning to strategic partnerships with traditional energy players and innovative storage solutions to meet both sustainability goals and reliability needs.
Elon Musk
SpaceX reveals reason for Starship v3 stand down, announces next launch date
SpaceX has decided to stand down from what was supposed to be the first test launch of Starship’s v3 rocket tonight after a minor issue with a hydraulic pin delayed the flight once more.
The company scrubbed its first test flight of the upgraded Starship v3 on May 21 in the final minutes of the countdown. SpaceX CEO Elon Musk quickly took to social media platform X, explaining that a hydraulic pin on the launch tower’s “chopsticks” arm failed to retract properly.
Musk added that the company would fix the issue this evening. SpaceX will attempt another launch tomorrow night at 5:30 p.m. CT, 6:30 p.m. ET, and 3:30 p.m. PT.
The hydraulic pin holding the tower arm in place did not retract.
If that can be fixed tonight, there will be another launch attempt tomorrow at 5:30 CT. https://t.co/DJAdvDYQpH
— Elon Musk (@elonmusk) May 21, 2026
The countdown for Starship Flight 12 — featuring the taller and more capable V3 stack with Booster 19 and Ship 39 — had been progressing smoothly until the late-stage issue surfaced. The Mechazilla tower arm, designed to secure the vehicle on the pad and eventually catch returning boosters, could not complete its retraction sequence.
SpaceX teams immediately began troubleshooting the hydraulic system for an overnight repair.
Starship V3 introduces several significant upgrades over earlier versions. These include greater propellant capacity, more powerful Raptor 3 engines, larger grid fins, enhanced heat shielding, and an improved fuel transfer system.
We covered the changes that were announced just days ago by SpaceX:
SpaceX unveils sweeping Starship V3 upgrades ahead of May 19 launch
The changes are intended to increase payload performance, support higher flight rates, and advance the vehicle toward operational missions, including Starlink deployments, NASA Artemis lunar landings, and future crewed Mars flights. The debut flight from Starbase’s new Launch Pad 2 marked an important milestone in scaling up the fully reusable Starship system.
This stand-down highlights the intricate challenges of preparing the world’s most powerful rocket for flight. Despite extensive pre-launch checks, a single component in the ground support equipment can force a scrub.
The incident aligns with Starship’s proven iterative development approach. Previous test flights have encountered both successes and setbacks, each providing critical data that refines hardware and procedures. Some outlets may call some of these flights “failures,” when in reality, they are all opportunities for SpaceX to learn for the next attempt.
With V3, SpaceX aims to reduce ground-system dependencies and increase launch cadence to meet ambitious long-term goals.