Tesla Gigafactory 3 obtains vital certificate after completing inspection in record time
The Tesla Gigafactory 3 in China received its first comprehensive acceptance certificate on Monday, following an inspection of the facility by government representatives. The certificate was granted to the electric car maker just three days after it made an application for the inspection, setting a new approval timing record from the local government.
It has only been ten months since Gigafactory 3’s land grant contract was signed, and only seven months since the actual construction of the general assembly building began. This, as noted by local news site The Paper, highlights the Chinese government’s efforts to foster a better business environment in the Shanghai area for innovative companies such as Tesla.
Similar to the other forms of support that Tesla has received in Shanghai, the local government appeared to have gone above and beyond to ensure that the facility’s comprehensive acceptance certificate will be expedited. On July 11, for example, the Lingang government established a special group to hasten the inspection progress of Tesla’s construction efforts. This was done as a way to meet its target of “finishing inspection when the construction is done,” according to a Global Times report.
It should be noted that the Lingang government is expected to benefit from the presence of Gigafactory 3 in its jurisdiction. Earlier this month, reports emerged revealing that the Lingang area, which covers 119.5 square kilometers, will be formally added to Shanghai’s Free Trade Zone. The addition of the Lingang area, which currently hosts Tesla’s upcoming electric car production facility, will roughly double the size of the FTZ.
Wang Shouwen, China’s vice-commerce minister who is among the country’s delegation to the United States, noted that the addition of Lingang to Shanghai’s Free Trade Zone was a decision that was fully supported by Beijing. “The expansion of the Shanghai FTZ is also an important step to demonstrate China’s clear stand for all-round opening up in the new era and its active role in guiding the healthy development of economic globalization,” Wang said.
The Gigafactory 3 site will likely be graced by a visit from CEO Elon Musk later this month, as the CEO is expected to be in Shanghai on August 29 to attend the 2019 World Artificial Intelligence Conference. Musk’s trip will not be limited to just speaking and attending a high-profile AI conference, as the CEO also announced on Twitter that he would also be launching The Boring Company China in the same trip. Local media reports have pointed to Musk paying a visit to the Gigafactory 3 complex after the 2019 World Artificial Intelligence Conference as well.
News
Tesla Model S and X customization options begin to thin as their closure nears
Tesla’s Online Design Studio for both vehicles now shows the first color option to be listed as “Sold Out,” as Lunar Silver is officially no longer available for the Model S or Model X. This color is exclusive to these cars and not available on the Model S or Model X.
Tesla Model S and Model X customization options are beginning to thin for the first time as the closure of the two “sentimental” vehicles nears.
We are officially seeing the first options disappear as Tesla begins to work toward ending production of the two cars and the options that are available to those vehicles specifically.
Tesla’s Online Design Studio for both vehicles now shows the first color option to be listed as “Sold Out,” as Lunar Silver is officially no longer available for the Model S or Model X. This color is exclusive to these cars and not available on the Model S or Model X.
🚨 Tesla Model S and Model X availability is thinning, as Tesla has officially shown that the Lunar Silver color option on both vehicles is officially sold out
To be fair, Frost Blue is still available so no need to freak out pic.twitter.com/YnwsDbsFOv
— TESLARATI (@Teslarati) February 25, 2026
Tesla is making way for the Optimus humanoid robot project at the Fremont Factory, where the Model S and Model X are produced. The two cars are low-volume models and do not contribute more than a few percent to Tesla’s yearly delivery figures.
With CEO Elon Musk confirming that the Model S and Model X would officially be phased out at the end of the quarter, some of the options are being thinned out.
This is an expected move considering Tesla’s plans for the two vehicles, as it will make for an easier process of transitioning that portion of the Fremont plant to cater to Optimus manufacturing. Additionally, this is likely one of the least popular colors, and Tesla is choosing to only keep around what it is seeing routine demand for.
During the Q4 Earnings Call in January, Musk confirmed the end of the Model S and Model X:
“It is time to bring the Model S and Model X programs to an end with an honorable discharge. It is time to bring the S/X programs to an end. It’s part of our overall shift to an autonomous future.”
Fremont will now build one million Optimus units per year as production is ramped.
News
Tesla Cybertruck Dual Motor AWD estimated delivery slips to early fall 2026
Tesla has also added a note on the Cybertruck design page stating that the vehicle’s price will increase after February 28.
Tesla’s estimated delivery window for new Cybertruck Dual Motor All-Wheel Drive (AWD) orders in the United States has shifted to September–October 2026. This suggests that the vehicle’s sub-$60,000 variant is now effectively sold out until then.
The updated timeline was highlighted in a post on X by Tesla watcher Sawyer Merritt, who noted that the estimated delivery window had moved from June 2026 to September-October 2026, “presumably due to strong demand.”
The Dual Motor AWD currently starts at $59,990 before incentives. Tesla has also added a note on the Cybertruck design page stating that the vehicle’s price will increase after February 28.
If demand remains steady, the combination of a later delivery window and a pending price increase suggests Tesla is seeing sustained interest in the newly-introduced Cybertruck configuration. This was highlighted by Elon Musk on X, when he noted that the Cybertruck Dual Motor AWD’s introductory price will only be available for a limited time.
When the Cybertruck was first unveiled in November 2019, Tesla listed the Dual Motor AWD variant at $49,990. Adjusted for inflation, that figure equates to roughly $63,000 in 2026 dollars, based on cumulative U.S. inflation since 2019.
That context makes a potential post-February price in the $64,000 to $65,000 range less surprising, especially as material, labor, and manufacturing costs have shifted significantly over the past several years.
While Tesla has not announced a specific new MSRP, the updated delivery timeline and pricing note together suggest that the Cybertruck Dual Motor AWD could very well be the variant that takes the all-electric full-sized pickup truck to more widespread adoption.
Elon Musk
SpaceX targets 150Mbps per user for upgraded Starlink Direct-to-Cell
If achieved, the 150Mbps goal would represent a significant jump from the current performance of Starlink Direct-to-Cell.
SpaceX is targeting peak download speeds of 150Mbps per user for its next-generation Direct-to-Cell Starlink service. The update was shared by SpaceX Spectrum & Regulatory Affairs Lead Udrivolf Pica during the International Telecommunication Union’s Space Connect conference.
“We are aiming at peak speeds of 150Mbps per user,” Pica said during the conference. “So something incredible if you think about the link budgets from space to the mobile phone.”
If achieved, the 150Mbps goal would represent a significant jump from the current performance of Starlink Direct-to-Cell.
Today, SpaceX’s cellular Starlink service, offered in partnership with T-Mobile under the T-Satellite brand, provides speeds of roughly 4Mbps per user. The service is designed primarily for texts, low-resolution video calls, and select apps in locations that traditionally have no cellular service.
By comparison, Ookla data shows median 5G download speeds of approximately 309Mbps for T-Mobile and 172Mbps for AT&T in the United States, as noted in a PCMag report. While 150Mbps would still trail the fastest terrestrial 5G networks, it would place satellite-to-phone broadband much closer to conventional carrier performance, even in remote areas.
Pica indicated that the upgraded system would support “video, voice, and data services, clearly,” moving beyond emergency connectivity and basic messaging use cases.
To reach that target, SpaceX plans to upgrade its existing Starlink Direct-to-Cell satellites and add significant new capacity. The company recently acquired access to radio spectrum from EchoStar, which Pica described as key to expanding throughput.Â
“More spectrum means a bigger pipeline, and this means that we can expand what we can do with partners. We can expand the quality of service. And again, we can do cellular broadband basically, cellular broadband use cases, like AI or daily connectivity needs,” he stated.
SpaceX has also requested regulatory approval to deploy 15,000 additional Direct-to-Cell satellites, beyond the roughly 650 currently supporting the system. The upgraded architecture is expected to begin rolling out in late 2027.