Connect with us

News

Installing Solar Panels through SolarCity

Published

on

Installing Solar Panels through SolarCityShortly after placing my order for my Tesla Model S I started looking into installing a solar panel system at home as a way to offset the soon-to-be increased electricity bill. My research turned me to a SolarCity system which I ended up signing up with in April of 2014.

After a number of scoping, design, and utility company challenges the day finally came for installation.

Sizing the Job

While I had originally hoped for a much larger system, the system that was installed was still large by most people’s standards. The final design called for 70 panels, each capable of generating 255W for a total of 17.8 kW and an annual expected output of 18,611 kWh.

To put that into perspective, my Model S uses an average of 775 kWh (as measured through a digital submeter) or approximately 2,400 miles. That usage will climb a bit for the winter months, but I still intend to use about 9,300 kWh per year for my Model S which equates to 50% of my expected solar generation capacity.

What this means is that I’ll be driving my Model S on 100% solar generated energy and still have solar energy to spare to offset my normal electric costs.

Many installations are half this size or smaller due to a number of constraints. Because of the size of this job, SolarCity booked 2 days for the install and sent a crew of about 8 to do the work.

Scheduling

SolarCity Panel StagingIt was a bit nerve wracking waiting for the project to begin 8 months after my April sign up date. This put us smack dab in the middle of winter for a December 8th install in New England. We’ve had snow and ice storms along the way which made me more skeptical that the install would ever take place.

I’m happy to report that the entire SolarCity team in charge of the project arrived on the scheduled date. They were late due to leftover work at a different site, but they turned up despite the wet weather, 30 degree temperature and got right to work. It was immediately evident that this crew knew what they were doing and it was just another day on the job despite the magnitude of the install.

Advertisement
-

Solar Panel Installation

Solar Mounting PointsThe first order of business was to tape off and secure the area from foot traffic. Anchors are attached to the roof which the crew secured their safety harnesses to.

Once the precautionary safety measures were in place, the crew began setting up dozens of anchor points across the roof surfaces later to be used as mounting points for the solar panels. That part took most of the first day.

By the end of the first day they had managed to install solar panels on the smaller of the 2 roof lines and had most of the anchors ready on the larger roof line.

Weather Proof Guarantee

A Noreaster hit right in the middle of the week so installation was postponed. To make matter worse, all of the heavy rain and cold weather ended up icing over the roof. I crawled into both attics below each roof to ensure that all of the nails and anchors on the roof didn’t create a leak and was relieved to find that everything was totally dry.

SolarCity guarantees a leak-free installation so it was great to be able to validate that even after torrential rains.

The crew returned on the third day despite the rain and proceeded to work a full day in extremely cold weather and light rain.

Uh oh, Design Challenges

Pipe out of placeTwo different design issues were uncovered during the solar panel installation. The first of which was related to a misjudgment on the number of solar panels that would fit. Designers back at corporate had mapped out 70 panels for the roof, but one of the panels would not fit behind the chimney. The crew offered to stick it somewhere else, but we declined as it would have been asymmetrical anywhere else and the aesthetics would not have been good. So we ended up with a total of 69 panels and a slight decrease in target generation capacity.

The second issue was identified on the third day. While the entire install was on the front of the house (thanks to National Grid), they had a pipe running in the middle of the roof on the rear of the house which looked stupid and unnecessary.

Advertisement
-

I spoke to them about it and they cheerfully redesigned and relocated the entire pipe. In the rain. In 30 degree weather. On top of the house. The install team took our concerns seriously and took care of the problem.

The Final Touches

Installing Solar Panels through SolarCityAfter lugging the panels up all day (each panel weighs about 45 pounds) and mounting them, they took the time to level each of them so they were completely flat.

At one point a single panel in the middle of the lot was a bit out of place (not perfect) so one of the guys had to slide down the wet, cold, glass on his knees (getting soaked in the process), 30 feet above ground with just a line to keep him safe just to adjust the angle slightly. Those installers are hard core!

Electric Connection

Solar InvertersI was surprised that SolarCity needed no access to the house (other than for bathroom breaks) to do the job. The entire connection for my house was on the outside. They needed to cut the power for about 45 minutes to connect into the mains but otherwise there was very little disruption.

The size of the installation required 3 inverters which they placed on the side of the house.

Next Steps

The process leading up to the install (3 part series) was frustrating and error-prone between the reluctant power company and the mistakes made by the out-of-touch engineers back at SolarCity corporate. But SolarCity’s installation team was nothing but first class, all the way. They knew their stuff, were very safety conscious and worked through some harsh conditions to get the job done, and done well. They restored my confidence in the decision I made and I’m confident again that things are going to work out well.

Now that the system is installed and ready to go we need to have the inspections done. SolarCity coordinates it all, but there’s a building inspection, an electrical inspection and then an inspection by the power company. Once all passes (in about 3-4 weeks) we’re given the green light to flip the switches and start putting that free energy from the sun to good use.

Advertisement
-

"Rob's passion is technology and gadgets. An engineer by profession and an executive and founder at several high tech startups Rob has a unique view on technology and some strong opinions. When he's not writing about Tesla

Advertisement
Comments

News

Tesla Giga Texas reportedly moves to 24/7 production

Published

on

Credit: @JoeTegtmeyer/X

Tesla’s Austin Gigafactory is reportedly shifting to round-the-clock vehicle production through the end of 2026, according to longtime drone observer Joe Tegtmeyer.

In his November 2 update, Tegtmeyer, widely regarded as one of the most reliable independent sources on Giga Texas activity (we call him the Drone GOAT), stated that the plant has added a night shift, creating two 12-hour production shifts.

Tegtmeyer said in his video:

“Now, I do have some interesting news about that when it comes to the production schedule here at Giga Texas, and things are actually looking pretty good, especially when you think about what the demand is and the delivery numbers that they’re looking for and what they’re expecting. So, normally they have shifts Monday through Friday. It’s a day shift and it’s about 10 hours long or so, give or take. But now they’re on day and night shifts and they’re going to 12-hour days. So they’re going to be adding or they have another shift. They have 12 hours for both of them. In addition to that, the typical downtime that we’re going to be seeing around the holidays, specifically Thanksgiving and Christmas to the New Year time frame is actually changed. And we’re not going to see those big several day events where there is no production. At least that’s what the plan is right now. So, it’s really a great sign, I think, when we consider what they’ve done in the past and what production and the deliveries have been so far. So, maybe it’s shaping up to be a really strong quarter.”

Previously, General Assembly typically operated on a single roughly 10-hour day shift, Monday through Thursday or Friday. The new arrangement keeps General Assembly on its Monday-to-Thursday schedule while adding overnight capacity, and most other areas of the factory continue working the full week with some weekend activity.

Notably, the plant is also forgoing the multi-day shutdowns around Thanksgiving and the Christmas–New Year period that have occurred in prior years

Advertisement
-

Giga Texas currently builds the Model Y, the larger Model Y L, the Cybertruck, and the Cybercab robotaxi. Tesla has not confirmed the shift change or specified which lines will receive the extra output. Recent comments suggest Cybercab production has been constrained by the pace at which the Robotaxi fleet can absorb new vehicles, making the Model Y and Model Y L the more likely beneficiaries as the company works through order backlogs.

Tegtmeyer’s November 2 footage and commentary also highlighted broader site progress. Cortex 2 continues to expand, with additional compute coming online, a roughly 25 percent lengthening of the structure on the north end, and work on a third cooling plant.

The Boring Company tunnel site showed increased activity in the large launch pit, while the Advanced Technology Chip Fab (a SpaceX–Tesla joint R&D facility) continued steel superstructure and heavy truss installation, along with concrete pours.

The reported capacity increase arrives as Tesla aims for a strong fourth quarter following solid third-quarter results. While unconfirmed by the company, the information aligns with Tegtmeyer’s consistent track record of accurate on-site observations.

If Tesla makes the decision to sustain the all-day production plans, the dual 12-hour shifts would meaningfully raise weekly output potential at one of Tesla’s most important manufacturing hubs.

Advertisement
-
Continue Reading

News

Tesla opens new “Cybaer” Engineering Center in Berlin

Tesla opened its Berlin Engineering Center, uniting four sites and 30 labs near Giga Berlin.

Published

on

By

Tesla has opened a new engineering hub in Berlin, putting the teams that design and test its European parts about 30 minutes from the factory that builds them.

The Berlin Tesla Engineering Center, or BTEC, opened Wednesday in the Köpenick district. Tesla Europe said on X that the project went from permit to operational in under a year and consolidates four engineering sites and 30 labs onto a single campus. It is the company’s third hub of this kind, after Fremont and Shanghai.

“We’re combining materials, powertrain, vehicle engineering & validation under one roof, enabling a short feedback loop between development & ramp,” Tesla Europe wrote.

 

Tesla converted the former production halls of a cable factory for the site. About 250 engineers and technicians are starting there, most of them relocated from existing Tesla facilities such as Tilburg in the Netherlands. Tesla has already applied for approval of a second phase that would take the headcount to roughly 500, and it put the total investment at €100 million.

Advertisement
-

The labs cover battery cells, motors, materials and complete vehicles, and a large hall is set aside for safety testing of components, including airbags. During the opening, staff demonstrated a pedestrian leg impact test on the front of a Tesla using a catapult rig, Tagesspiegel reported. The center’s logo is a cubist Berlin bear that employees call the “Cybaer.”

Tesla said its Berlin design and engineering teams already contributed to the Model Y, Semi and Roadster, and that the work continues at BTEC. The center will handle technical problem solving for Giga Berlin in Grünheide while also developing and validating parts for vehicles built in China and the United States.

“We came here to stay,” BTEC head Brückner told dpa. “We serve all of Europe via Gigafactory Berlin-Brandenburg.” He said a site close to the plant was a priority, and that the old industrial building allowed Tesla to move quickly.

That proximity matters more now that Giga Berlin is growing again. In June, Tesla said it would raise Model Y output at the plant to 7,500 vehicles per week and hire 1,000 more workers after a record first quarter of more than 61,000 units. The factory recently built 7,000 Model Ys in a single week for the first time. Tesla also more than doubled the planned 4680 cell capacity at the site to 18 GWh per year in May, and has talked about eventually taking Grünheide to one million vehicles annually.

Sales are giving Tesla reason to invest. KBA data released the same day showed Tesla’s German registrations nearly quadrupled year over year in October to 2,932 units, bringing the total for the first ten months of 2026 to 47,742.

Advertisement
-
Continue Reading

News

Ferrari Luce sold out for 2027 after design controversy

Published

on

Credit: Ferrari

Ferrari’s first electric vehicle, the Luce, is fully sold out for 2027, according to CEO Benedetto Vigna.

Presenting third-quarter results, he stated: “Everything we plan to sell next year is already fully allocated. Client test drives, scheduled for next year, will help further boost demand. We have no critical issues, neither on manufacturing nor on the demand side. Obviously, the car is more complex because it has many new parts and many new technologies.”

First customer deliveries are expected before the end of 2026, with the model already commanding waitlists despite a turbulent debut.

The Luce is a five-seat, four-door liftback saloon—the longest Ferrari ever produced—powered by four electric motors producing approximately 1,035 horsepower.

It features an 800-volt architecture, a 122-kWh battery, a claimed WLTP range of around 329 miles, 0-62 mph acceleration in 2.5 seconds, and a starting price near €550,000 in Europe (roughly $560,800–$615,000 in the U.S. depending on configuration).

Developed in collaboration with Jony Ive and Marc Newson’s LoveFrom studio alongside Ferrari’s own Centro Stile, it represents a deliberate departure from the brand’s traditional mid-engine sports cars toward a more spacious, grand-touring format.

Its exterior has proven deeply polarizing. Unveiled in Rome in May 2026, the design features smooth, sweeping surfaces, a large glass roof, and restrained detailing that critics described as bland, generic, or more reminiscent of an Apple product or mass-market EV than a Ferrari.

Ferrari unveils its Luce EV, and its reception has been a disaster

Online reactions included memes comparing it to a Nissan Leaf or Polestar, while former Ferrari chairman Luca di Montezemolo publicly warned of “the destruction of a myth” and suggested the prancing horse logo be removed. Italian politicians and longtime owners joined the chorus of disappointment, and Ferrari’s shares dropped roughly 8% in a single day, erasing billions in market value.

Design experts noted the absence of the brand’s signature tension, aggression, and emotional drama.

Yet the controversy has not translated into weak demand among the ultra-wealthy clientele who actually buy Ferraris. Production volumes remain tightly limited, as reports suggest fewer than 500 units in the current year and a longer-term pace of roughly 600 annually through 2030, preserving exclusivity.

One early chassis sold for $40 million at auction. Vigna has indicated that seeing the car in person, along with upcoming client test drives, is expected to strengthen rather than weaken interest. Ferrari aims for fully electric models to comprise 20 percent of its lineup by 2030, with a second EV now delayed to 2028.

For a brand defined by scarcity and desirability, the Luce’s sell-out status suggests that among those who can afford it, the polarizing design has not proven to be a commercial liability.

Continue Reading