Tesla formally wins final environmental approval to open Gigafactory Berlin
The wait is finally over. After a long process that saw delays, controversies, and other drama, Tesla Gigafactory Berlin has won its final environmental approval from Germany. An official document confirming the update was published by the State of Brandenburg, outlining the next steps that the electric vehicle maker needs to do to start vehicle production in its Germany-based electric vehicle factory.
As per the state’s press release, the approval for Giga Berlin covers several activities, such as the production of up to 500,000 vehicles per year. The approval also includes battery cell production activities within the Giga Berlin complex, which should allow Tesla to manufacture its in-house cells from within Germany.
“The project, which was approved with the 536-page decision, includes the plant for the production of up to 500,000 vehicles per year, aluminum smelting plants and an aluminum foundry, plants for surface treatment, heat generation, and storage. The facility also includes battery cell production, an operational wastewater treatment plant, a fire brigade equipment house, a high-bay warehouse, as well as laboratories and workshops,” the press release read.

It should be noted that while it may have taken two years to get to this point, Gigafactory Berlin’s formal approval was still completed in a quick manner, at least relatively speaking. The past two years, after all, required the State Office of the Environment to not only inspect and approve the factory itself, but also the entire industrial area with several large-scale facilities. Environment Minister Alex Vogel expressed his thanks to the state’s employees and other authorities for Giga Berlin’s quick approval process.
“As a high-performing state administration, you have always focused on the technical requirements, the high level of protection of the environment, the protection of the general public and the neighborhood from dangers, even under the pressure of great public interest and unreasonable harassment as well as the legal certainty of the procedure. In times of climate crisis, the availability of water will play an increasingly important role for future developments and settlements. Above all, digitization can help to simplify and accelerate processes without restricting environmental standards and participation rights,” Vogel said.
District Administrator Rolf Lindemann emphasized that Giga Berlin benefits the region. The fact that the project faced much adversity, and was still able to achieve a milestone such as a final environmental approval in a relatively short time, proves that the project’s potential is vast. He also noted that Giga Berlin, as well as those that have been working with Tesla over the past two years to approve the project, shall face whatever challenges lie ahead with vigor.
“The Oder-Spree district described the Tesla Gigafactory as a real stroke of luck for the development of our region. We have therefore mobilized all our strength to help turn this unique opportunity into a visible success. It wasn’t always easy, and we’re anything but done when it comes to the final form of the overall project. But we all have reason to be proud of what we have achieved so far, despite all prophecies of doom.
“That is why we will face the further challenges that lie ahead with confidence and with undiminished vigor. I am referring to the official support of the further expansion stages, the completion of the battery factory and of great importance, especially for local politics: as far as possible, a stress-free integration of the Gigafactory into the traffic infrastructure . However, in order to be able to meet the sustainability aspect and smooth mobility in connection with production, it is of course necessary to start building housing close to the location and to create the associated social infrastructure. We trust in the same support from the state government that we have been able to rely on in the past,” Lindemann said.

While Giga Berlin’s final environment approval has been secured, Tesla still has to ensure that it meets the state’s requirements. These are highlighted by the mammoth size of its approval documents, which comprise over 23,700 pages in 66 files. More than 400 ancillary provisions are included, involving topics such as requirements for groundwater protection as well as water-saving and wastewater-reducing measures, species protection measures, limit values for air pollutants and regulations on their measurement as well as occupational safety requirements. Other specific rules on the plant’s operations, particularly with regards to how it affects the area’s groundwater, were also highlighted in the press release.
“There are 113 air pollution control requirements, which include respective chimney heights for each exhaust air stream. In addition, 22 requirements determine the methods and intervals at which the exhaust air is to be measured. 96 requirements for drinking water protection, waste water disposal and rainwater specify, among other things, limit values for discharge into the waste water pressure line and corresponding cleaning processes. When using building materials, it is important to ensure that no harmful substances get into the groundwater. With groundwater monitoring, both the formation of new groundwater and the quality of the groundwater must be checked regularly. In view of the tense water situation, not least due to climate change, it should be possible to react to changes as early as possible.
“After the inspection by the approval authority, the entire system falls under the provisions of the Hazardous Incidents Ordinance (12th BImSchV) and must therefore take special precautions to prevent incidents and limit the effects of incidents, as well as maintain an appropriate safety distance from adjacent protected objects. Tesla must draw up an incident concept and comply with special information obligations,” the press release read.
The state noted that Tesla may now start or continue with the further construction of Giga Berlin and that objections to the project now have “no suspensive effect.” It should be noted, however, that before Tesla can actually put its Model Y production facility into operation, several ancillary provisions must be met first. These provisions, which include the installation of measuring devices for air pollutants and precautions for fire protection and accidents, will be checked by the responsible authorities. Once Tesla completes this step, Model Y production for customer vehicles could finally commence.
Needless to say, all eyes are now focused on how quickly Tesla can meet the requirements for Giga Berlin’s operational permit.
Don’t hesitate to contact us with news tips. Just send a message to simon@teslarati.com to give us a heads up.
News
Tesla expands massive safety feature worldwide in latest update
Tesla has expanded the footprint of a massive safety feature worldwide with a recent Software Update labeled as 2026.20.6. The expansion of the “Blind Spot Warning While Parked” feature represents the more widespread availability of the feature, which aims to prevent “dooring.”
Dooring is when a driver or passenger opens a car door into the path of an oncoming road user, usually a cyclist or motorcyclist. It is among the most common types of cycling accidents, the League of American Bicyclists says.
For this reason, Tesla created a feature that warns occupants not to open the door because an object is approaching. The feature will sound a chime, and it will also delay the opening of the door to prevent an incident.
The release notes state (via Not a Tesla App):
“If you attempt to open a door while an approaching object is detected in your blind spot (for example, a bicyclist approaching from behind) a chime sounds, and your door will not open upon initial button press. Wait a short time and press the button a second time to override the warning.”
Tesla initially rolled out this feature back in 2024 with the Model 3 “Highland.” However, it remained with the Model 3 exclusively for over a year; that was until Tesla added it to the Cybertruck this past Spring.
Now, it is making its way to the new Model Y, 2021 and newer Model S, and 2021 or newer Model X.
The prevention of dooring incidents could eliminate many injuries to cyclists, especially in an urban setting. Dooring accounts for 10-20 percent of bike-related crashes in major cities, and over 17,000 dooring-related incidents were treated in the U.S. over the course of a decade. These usually involve fractures, contusions, and head trauma.
News
Tesla sends production Cybercab with no steering wheel, pedals to on-road testing
Tesla confirmed this morning that it has sent the first production units, manufactured with no steering wheel or pedals, to on-road testing in Austin, sharing video of the first rides with no human controls.
The lack of steering wheels and pedals in the Cybercab aligns with Tesla’s self-certification of Robotaxi as Level 4 SAE, a platform it plans to make widespread through internal vehicles and customer-owned cars that will operate and generate revenue for individuals.
The start of these engineering tests is a major signal for Tesla, which plans to bring driverless, wheel-less, and pedal-less Cybercabs to market in the coming months. With production already well underway at Gigafactory Texas, where the Cybercab is built, there is some inclination to believe the first public rides could happen sooner rather than later.
Engineering tests of the first production Cybercab have begun in Austin pic.twitter.com/fk3KQvcE8a
— Tesla (@Tesla) June 30, 2026
Tesla’s engineering tests will put the Cybercab in real-world scenarios, testing not only the hardware, but more importantly, the software that drives the car around Austin with nobody supervising it within the car.
This is perhaps the biggest part of the internal testing process, especially prior to allowing regular, everyday people to hail the Cybercab for an autonomous ride. These early rides serve as a true benchmark for Tesla: How many rides can it achieve safely? How many miles did it travel consecutively without needing an intervention? What scenarios challenge the Full Self-Driving suite the most?
The proper precautions have already been put into place as well, as Tesla released the First Responders Guide to Cybercab over the weekend, ensuring that emergency services have 24/7 access to Robotaxi Assistance, as well as other boundaries, such as Geofencing features that can be used to redirect autonomous vehicle traffic due to accidents, road closures, construction, or maintenance.
Cybercab seems genuinely close to being added to the Robotaxi fleet in Austin, but Tesla has prioritized safety throughout this entire process. Therefore, we think it could be months before it truly starts giving rides to the public. People have been frustrated with this, but Robotaxi in Austin has a tremendous safety record so far, so the slow rollout has kept people safe and accidents to a minimum.
The most important thing is that Tesla continues to show consistent progress in the Cybercab’s ramp-up toward fleet addition. A few weeks back, we saw the EPA reward the Cybercab a Certificate of Conformity, allowing it to enter the stream of commerce. Then, we saw Tesla add decals, signaling that it was likely about to start testing it publicly. That has now happened.
The next big move will be the announcement of the first rides, so this Summer should be filled with anticipation.
Elon Musk
Tesla Phone? Not quite, but close: analyst
For years, there have been images and videos across social media platforms that have reminded me of when I was a 15-year-old kid teased by “Xbox 720” videos on YouTube. These videos are of the supposed “Tesla Phone” that Elon Musk was secretly developing in between leading Tesla with its electric cars and SpaceX with its reusable rockets.
Would you buy a Tesla phone ? pic.twitter.com/aaTwvvIJit
— Tesla Owners Silicon Valley (@teslaownersSV) October 6, 2023
Although Musk has put those rumors to bed several times, it was never completely out of the realm that he could get involved in cell phones in some capacity. Think outside the box and more macro-level, though. Instead of reinventing the computer, Musk reinvented connectivity by developing Starlink with SpaceX.
It could be something similar, TD Cowen analyst Gregory Williams said in a note last week, where he hinted SpaceX could be gathering some steam to acquire T-Mobile.
Williams said it would be the “clear choice” for SpaceX if it decided to go through with a network acquisition. He also suggested AT&T.
The move would be possible through selling more of its own stock, which would help SpaceX raise the money to purchase T-Mobile, which would cost roughly $300 billion. It could be one of the moves SpaceX makes post-IPO in terms of an acquisition: it already acquired Cursor AI for $60 billion.
Other analysts, like Dan Ives of Wedbush, believe SpaceX and Tesla will eventually merge into one anyway, and that conglomeration could come as soon as this year, some have said.
The implications of SpaceX purchasing T-Mobile are massive. A combined entity would create a truly ubiquitous network: T-Mobile’s terrestrial 5G towers and Starlink’s growing constellation of Direct-to-Cell satellites. This would essentially eliminate dead zones across the U.S. and potentially globally.
SpaceX would instantly become a full-scale facilities-based carrier with satellite differentiation; a huge advantage. This would pressure AT&T and Verizon heavily.
There are also concerns like a potential reduction in long-term competition, and of course, a deal of that size would face intense scrutiny from government agencies.
The strategic fit is compelling due to the existing Starlink–T-Mobile partnership and complementary technologies (space + terrestrial). It could create a dominant integrated communications player. However, the regulatory, financial, and execution hurdles are enormous — this remains highly speculative with no indication SpaceX is actively pursuing it right now.