Tesla’s big battery in South Australia, the Hornsdale Power Reserve, recently hit another milestone as it entered the final testing phase of its recent expansion. With such performance, it appears that Tesla’s Powerpack farm, currently one of the world’s largest battery installations, will still be providing the region with industry-leading renewable services for the foreseeable future. 

The Hornsdale Power Reserve has been impressive from the time it was installed. Constructed in about 100 days partly due to a bet between Tesla CEO Elon Musk and Atlassian co-founder Mike Cannon-Brookes, the massive 100MW/129MWh battery installation promptly played a key part in providing frequency control and emergency back-up energy services to South Australia’s grid. 

The battery farm’s performance has been so impressive that it was expanded to a capacity of 150MW/194MWh. With this expansion comes new services like synthetic inertia, a function that has long been dominated by fossil fuel-powered generators. Currently, the expanded battery installation is going through testing that allows the system to progress through a number of “hold points.” And so far, recent observations indicate that the upgraded battery is poised to be even more disruptive once it’s fully operational. 

During its tests on Tuesday, for example, the upgraded Hornsdale battery performed a rapid 270MW flip by charging at 120MW and discharging at 150MW. As noted in a Renew Economy report, the battery installation appears to have performed the flip on several different occasions, and at least one of them had an impact on the wholesale price of electricity in the area. During one such flip, the expanded Tesla Powerpack farm pushed down power prices to just above AU$8 per MW. 

“Those 270MW flips – from the level of discharge to the level of charge – are likely a world record in both speed and extent of the change. And it’s this flexibility of the big batteries such as Hornsdale, and others at Dalrymple North, Lake Bonney, Gannawarra and Ballarat, that is particularly attractive to project owners and valuable to AEMO, the market operator,” the Australian publication noted. 

The Australian Energy Market Operator has lauded the Hornsdale big battery on several occasions for its speed, accuracy, and flexibility. Its undeniable breakthroughs in the energy sector have inspired what could very well be described as a battery storage movement in Australia. Apart from the expansion of the Hornsdale Power Reserve, Neoen Australia is also expected to construct a massive 600MW/1200MWh system in Victoria. The Victoria project will dwarf even the upgraded Hornsdale battery when it is completed, and it is poised to utilize Tesla Energy’s flagship energy storage product, the Megapack. 

Simon is an experienced automotive reporter with a passion for electric cars and clean energy. Fascinated by the world envisioned by Elon Musk, he hopes to make it to Mars (at least as a tourist) someday. For stories or tips--or even to just say a simple hello--send a message to his email, simon@teslarati.com or his handle on X, @ResidentSponge.

Advertisement
Comments

Energy

Tesla launches Powerwall Lease for affordable home backup

Published

on

Credit: Tesla

Tesla Energy has introduced the Powerwall Lease in conjunction with Tesla Electric, making the service available in Texas. This new option delivers whole-home backup power using two Powerwall units for a net monthly cost of $35 after credits, accompanied by a low fixed electricity rate.

Under the lease terms, customers pay a one-time order fee of $100. The base lease payment for the two Powerwalls is approximately $122 per month during the first year, subject to a 3 percent annual escalator thereafter. Enrollment in a qualifying Tesla Electric Backup plan or Virtual Power Plant plan provides an $87 monthly credit.

This credit lowers the effective cost to roughly $35 per month plus applicable tax.

Installation of the standard system carries no additional charge. The package features Storm Watch for outage protection and allows complete management through a single Tesla application. The system supplies continuous whole-home backup capability.

The Powerwall system enables households to maintain electricity during severe storms that disrupt the utility grid. When outages occur, the batteries automatically provide seamless backup power to the home.

Tesla announces 100k Powerwalls are participating in Virtual Power Plants

Tesla Storm Watch monitors weather forecasts and ensures the units are fully charged ahead of anticipated severe weather events so that power remains available throughout the disruption, keeping lights, refrigeration, and other essential systems operating without interruption.

Availability is restricted to select Texas locations where retail electric choice exists. Participants must lease exactly two Powerwall units and maintain continuous enrollment with Tesla Electric. Solar panels cannot be included under this particular lease arrangement.

The monthly credit activates automatically once the system is installed, receives permission to operate, and enrollment is confirmed. To retain the credit, customers are required to stay enrolled in Tesla Electric and fulfill all program conditions.

Nonstandard installations that involve electrical upgrades or special permitting may lead to extra expenses and might impact eligibility for the credit, so be sure to check with either your installer or Tesla to ensure you will still qualify.

Continue Reading

Elon Musk

Inside Tesla’s secretive $10 Billion “Project Crystal Sun” filing

Tesla filed for a $10.1 billion Fort Bend solar factory, but the site isn’t confirmed.

Published

on

By

Tesla has filed paperwork in Texas for a second massive manufacturing project in the same week it locked down its chip fabrication site, this time for a $10.1 billion solar cell plant in Fort Bend County. The filing, submitted July 22 under the state’s Jobs, Energy, Technology and Innovation Act and first surfaced by Sawyer Merritt on X, lists an internal project name of “Project Crystal Sun” and targets a site off FM 762 and FM 1994 near Richmond, about 40 minutes outside Houston.

The application, prepared by Kroll Tax Services on Tesla’s behalf, spans five parcels totaling roughly 3,000 acres within the Lamar Consolidated Independent School District. Tesla wants a 10 year property tax limitation in exchange for the investment, split as $1.5 billion in real property and $8.6 billion in equipment and personal property. The company projects 9,712 permanent jobs once the plant reaches full operation, with 1,147 peak construction jobs during a build window running from this year through 2028 and commercial operations targeted for the first quarter of 2029.

Tesla is not fully committed to Fort Bend County yet. The filing states the company is weighing the site against an unnamed out of state alternative, and frames the tax abatement as what would make Texas competitive against that option. If the district and county decline the incentive, Tesla says it may build elsewhere.

Tesla Megapack Megafactory in Texas advances with major property sale

The plant would handle the full solar cell production chain in one facility, according to the filing, covering wafer and ingot manufacturing, coating, metallization and printing lines, cell testing, automated material handling and cleanroom infrastructure. That scope points to Tesla vertically integrating a part of its supply chain it currently sources largely from overseas partners, mirroring the approach behind its expanding Megapack production in Brookshire, Texas, where Tesla has already built out two buildings for its grid battery business.

The timing lines up closely with Tesla and SpaceX’s other big Texas commitment this month. SpaceX confirmed its Terafab chip factory would land in Grimes County days before this filing surfaced, with construction on that $16.8 billion project starting almost immediately after local officials met with residents. Terafab is meant to produce the AI chips running Tesla’s Optimus robots and Full Self-Driving software, while a solar cell plant would feed a different part of the business, the panels and storage systems Tesla sells to homeowners, businesses and utilities, and increasingly needs to power its own data centers.

Musk has talked about building domestic solar manufacturing capacity before, tying it to the amount of power Tesla’s AI ambitions will require.

Continue Reading

Elon Musk

Tesla just trademarked MEGAPOD: here’s what it is

Published

on

tesla showroom
(Credit: Tesla)

Tesla just trademarked ‘MEGAPOD’ with the United States Patent and Trademark Office (USPTO), its latest move in what seems to be a hint that the company is incredibly focused on its AI efforts and storage needs as compute increases.

The application carries serial number 99893717 and lists the applicant as Tesla, Inc., located at 1 Tesla Road, Austin, Texas 78725.

The filing remains in ‘live pending’ status, and it is a new application waiting for assignment to an examining attorney. It has not yet been published or registered.

According to the official goods and services description in the application, Tesla describes ‘MEGAPOD’ as:

“Modular data center hardware systems for artificial intelligence computing, comprised of computer servers, computer hardware for artificial intelligence processing, computer networking hardware, electrical power distribution units, and cooling systems, sold as a unit; self-contained modular computing hardware systems for artificial intelligence workloads; integrated computer hardware platforms for artificial intelligence computing, namely, enclosures containing computer hardware, power distribution hardware, and cooling hardware, sold as a unit; downloadable software for monitoring, managing, optimizing, and regulating modular artificial intelligence computing hardware systems.”

This description specifies complete, self-contained modular units that integrate servers and specialized AI processing hardware with networking components, power distribution, and cooling systems. It also includes associated downloadable software for oversight and optimization of these systems. The language emphasizes hardware sold “as a unit” and enclosures that combine the necessary elements for AI computing workloads.

Tesla has an established history of developing and commercializing modular hardware systems. Its Megapack product line, for example, consists of utility-scale battery energy storage systems designed as containerized units for grid applications. The MEGAPOD filing follows a similar pattern of protecting a name for modular, integrated hardware platforms, this time focused on artificial intelligence computing infrastructure.

This could be an early move, especially as Tesla did not have trademark rights to the word ‘Cybercab,’ the name of its self-driving, ride-hailing-focused vehicle.

Trademark applications of this type allow companies to secure priority rights to a name for defined categories of goods and services. The USPTO examines applications for compliance with legal requirements, including distinctiveness and absence of conflicts with prior marks. If the application proceeds successfully through examination, publication, and any opposition period, it could result in a federal trademark registration providing nationwide protection. This is what Tesla’s obvious intention is with ‘MEGAPOD.’

Public reports and analysis suggest MEGAPOD could represent modular, container-style AI computing pods designed for easy deployment. These would bundle servers, AI accelerators, power systems, and cooling into self-contained units suitable for distributed AI workloads. This approach aligns with Tesla’s announced AI compute strategy.

In March 2026, Elon Musk outlined plans for “Digital Optimus” (also referred to as Macrohard), a joint Tesla-xAI project for AI agents capable of handling complex digital tasks. The plans include running these agents on Tesla’s AI4 hardware in parked vehicles as well as dedicated compute units installed at Supercharger stations, which collectively offer substantial unused electrical capacity.

What is Digital Optimus? The new Tesla and xAI project explained

A modular hardware platform like the one described in the ‘MEGAPOD’ filing would support scalable, rapid deployment of such distributed compute resources. It could complement Tesla’s other AI infrastructure efforts, including the Dojo supercomputer used for training models and the development of AI systems for autonomous driving and robotics, by enabling edge or regional AI inference without reliance on traditional centralized data centers.

Continue Reading